INSP-Final Inspection | 5/21/2007 | 5/21/2007 | 5/21/2007 | P | PASS |
Forrest France
|
|
|
Corrections verified, fire sprinkler permit finaled.
|
INSP-Final Inspection | 5/17/2007 | 5/18/2007 | 5/18/2007 | A | FAIL |
Troy Cobbley
|
|
|
The singel pendant installed in the back dressing room is standard instead of quick responce
|
INSP-Final Inspection | 5/15/2007 | 5/16/2007 | 5/16/2007 | A | NR |
Forrest France
|
|
|
Final pending testing of the riser supervision, also need to verifiy items noted at the previous inspection completed on 5/4-see activities under permit FIR06-00939- including missing coverage above the drop ceilings north of the kitchen area, one SSU is blocked at a storage room by a roof access hatch, missing hanger at one east branch line, no approved plans were on site as required.
|
INSP-Sprinkler Rough-in/Hydro | 5/3/2007 | 5/4/2007 | 5/4/2007 | A | PART |
Forrest France
|
|
|
UG and OH hydrostatic tests completed, noted UG leakage within allowable limits.
|
INSP-Supply line flush | 5/1/2007 | 5/1/2007 | 5/1/2007 | P | DONE |
|
|
|
Witnessed sprinkler supply flush by phoenix fire
|
INSP-Sprinkler Rough-in/Hydro | 3/14/2007 | 3/15/2007 | 3/15/2007 | P | PART |
Forrest France
|
|
|
Fire sprinkler install is good for cover at the restroom hard lids and the entryway vestibule soffits as noted on approved plans, will require as-builts reflecting all field modifications.
|
Issue and Print Permit | | | 1/29/2007 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/26/2007 | | DONE |
|
|
|
|
Telephone call | | | 1/26/2007 | | DONE |
|
|
|
tlk to trent bice that permit and fees are ready to be picked up
|
Inspection Record Card- Fire | 1/24/2007 | | 1/24/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 12/21/2007 | | 1/9/2007 | | PASS |
|
|
|
Plan review by Bryan Johnson with Conditions (Cant release this permit until bldg permit is picked up and paid)
|
Application received | | | 12/21/2006 | | |
|
|
|
|
Pending Assignment by SAM | 12/21/2006 | | | | |
|
|
|
|