Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR06-01023
StatusExpired
Name DEBEST FIRE PROTECTION
Site Address 101 N 10TH ST Unit: 207
Project NameGEM NOBLE BLDG
Customer Number 
ePlanReview 
Description
TI modification to shell sprinkler system installed under FIR06-00351.Add and relocate sprinklers on the second floor to accommodate a new wall and ceiling layout.
This permit is attached to BLD06-00704, FIR06—00351 / Shell & Core, UG permit FIR06-00226. . The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. Occupancy is not permitted until the Fire Department has certified by signature on the issued Permit by the Boise City Building Department, that the Shell & Core FIR06-00351) fire sprinkler system installation has been inspected and installed in compliance with an approved Fire Department inspection review. (IFC 105.3.3)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permit EXPIRED  3/15/2010 DONE
This work was completed by Idaho Fire Protection under permit FIR09-00196
Case Summary  3/11/2008 DONE
INSP-Sprinkler Rough-in/Hydro2/27/20072/28/20072/28/2007AFAIL
DetailsForrest France
Missing seismic bracing at the main, field mods will require as-built plans.
INSP-Sprinkler Rough-in/Hydro2/23/20072/27/20072/27/2007PFAIL
DetailsForrest France
Provide approved plans on site as required.
Issue and Print Permit  1/19/2007 DONE
Sprinkler Plan Check1/11/2007 1/18/2007 PASS
Plan review by Bryan Johnson
PLANS/APPL TAKEN TO FRONT DESK  1/18/2007 PASS
Inspection Record Card- Fire1/18/2007 1/18/2007 DONE
Permit Ready to Issue  1/18/2007 DONE
Telephone call  1/18/2007 DONE
tlk to secretary for keith dilworht ###-#### that permit and fees are ready to be picked up
Plan resubmittals received  1/11/2007 DONE
Brian, We got your comments and I have spoken with Donny who
submitted the drawings. The approved shell and core plans for the Gem Noble Project included all of the design work for the second
floor/tenants included. After we submitted and were approved the
owner/general contractor pulled individual tenant BLD#'s for each space. After discussions with Sam Rogers we resubmitted the same plans we submitted for the shell and core attaching the individual BLD#'s to each condo unit. There is no difference between the shell and core/tenant build out except that we need individual FIR#'s to call for inspections under. Donny will make all the other necessary revisions, I will have color code the outline of each condo unit with the appropriate BLD. Unusual circumstance, please call with any questions Thanks Keith Dilworth DeBest Fire Protection
Case Summary  1/11/2007 DONE
Application received  12/29/2006  
Pending Assignment by SAM12/29/2006