INSP-Final Inspection | 2/15/2007 | 2/15/2007 | 2/15/2007 | P | PASS |
Forrest France
|
|
|
Final fire sprinkler inspection passed, permit finaled.
|
INSP-Final Inspection | 2/6/2007 | 2/7/2007 | 2/7/2007 | A | FAIL |
Troy Cobbley
|
|
|
Ceiling tile is not installed and the approved plans are still not on site.
|
INSP-Final Inspection | 2/6/2007 | 2/6/2007 | 2/6/2007 | P | FAIL |
Troy Cobbley
|
|
|
Need ceiling tile installed and approved plans on site for me to verify that what is should be.
|
INSP-Sprinkler Rough-in/Hydro | 1/29/2007 | 1/30/2007 | 1/30/2007 | A | PART |
Forrest France
|
|
|
Required corrections have been verified, OH rough-in approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 1/26/2007 | 1/29/2007 | 1/29/2007 | P | NR |
Forrest France
|
|
|
Required work is not yet complete for inspection.
|
INSP-Sprinkler Rough-in/Hydro | 1/25/2007 | 1/26/2007 | 1/26/2007 | A | FAIL |
Forrest France
|
|
|
Noted locations on approved plan set which are in need of revision including missing head placement and obstructed heads.
|
INSP-Sprinkler Rough-in/Hydro | 1/24/2007 | 1/24/2007 | 1/26/2007 | P | DEFR |
Forrest France
|
|
|
Inspection to be completed as scheduled on 1/26.
|
Issue and Print Permit | | | 1/12/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 1/10/2007 | | 1/11/2007 | | DONE |
|
|
|
Plan review by Bryan Johnson
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/11/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 1/11/2007 | | 1/11/2007 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/11/2007 | | DONE |
|
|
|
|
Telephone call | | | 1/11/2007 | | DONE |
|
|
|
tlk to secretary for randy bowron ###-#### that permit and fees are ready to be picked up
|
Application received | | | 1/3/2007 | | |
|
|
|
|
Pending Assignment by SAM | 1/3/2007 | | | | |
|
|
|
|