INSP-Final Inspection | 12/6/2007 | 12/6/2007 | 12/6/2007 | P | PASS |
Forrest France
|
|
|
Accepted as-built plans, permit finaled.
|
INSP-Final Inspection | 12/5/2007 | 12/5/2007 | 12/5/2007 | P | FAIL |
Forrest France
|
|
|
Contractor needs to provide two copies of as-built plans.
|
INSP-Final Inspection | 11/30/2007 | 12/3/2007 | 12/3/2007 | A | FAIL |
Forrest France
|
|
|
Approved plans were not on site at the time of inspection, also need to provide as-builts for field modifications.
|
INSP-Sprinkler Rough-in | 10/29/2007 | 10/30/2007 | 10/31/2007 | P | DEFR |
Forrest France
|
|
|
See inspection notes under the shell permit.
|
INSP-Sprinkler Rough-in/Hydro | 10/25/2007 | 10/26/2007 | 10/29/2007 | P | PART |
Forrest France
|
|
|
Hydro test passed.
|
INSP-Sprinkler Rough-in | 8/16/2007 | 8/17/2007 | 8/17/2007 | A | NR |
Forrest France
|
|
|
Pending light fixture obstruction issues.
|
FIR-Aging Inspection | 7/23/2007 | 7/23/2007 | 7/24/2007 | | DONE |
Forrest France
|
|
|
Work in progress.
|
Issue and Print Permit | | | 4/4/2007 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/2/2007 | | |
|
|
|
|
Telephone call | | | 4/2/2007 | | DONE |
|
|
|
t/c w lilly at shilo ###-#### - permit ready and fees given ($150.00)
|
Inspection Record Card- Fire | 1/22/2007 | | 1/22/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 1/8/2007 | | 1/19/2007 | | PASS |
|
|
|
Plan review by Bryan Johnson
|
Application received | | | 1/8/2007 | | |
|
|
|
|
Pending Assignment by SAM | 1/8/2007 | | | | |
|
|
|
|