Permit Information
Permit NumberFIR07-00046
StatusVoid/No Violation
Name DEBEST FIRE PROTECTION
Site Address 2051 S COLE RD
Project NameSPR-Costco Cooler
Customer Number 
ePlanReview 
Description
**(CostCo)** To expand an existing walk-in cooler in the produce department per approved plans. Work to include, installation of prefab cooler walls, installation of lighting, relocation of floor drains, and modification to the sprinkler system. NOTE A SEPARATE PERMIT REQUIRED FOR ANY MODIFICATION TO THE SPRINKLER SYSTEM and shall be installed per NFPA #13 as regulated by the fire department. Debest Fire Protection to add 12 DSSP heads in new addition walk in cooler and relocate 13 exisitng DSSP heads to accomodate modifications.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permit VOIDED9/24/20079/24/20079/24/2007 DONE
void permit per Sam Rogers, this company no longer working on this project; replaced with fir07-00793
Telephone call  8/22/2007 DONE
Telcon with Randy, DeBest (###-####); they are to be replaced with another sprinkler contractor to redesign the system for 19' hi stge of Class II commdity (fruits and vegies in wooden and multi-ply CB crates, in single row racks without IR's, ord temp ceiling spk's; req's 0.34/2000sf density (avail density is 0.15). When new plans are submitted from a new contractor, this permit is to be voided and replaced with a new permit for the new contractor).
INSP-Sprinkler Rough-in/Hydro2/26/20072/27/20072/27/2007AFAIL
DetailsTroy Cobbley
Per the drawings and a subsequent phone conversation with Randy at DeBest, the sprinkler system in the coolers is designed for a .15 gpm density and is limited to a maximum storage height of 12'-0". The storage height as measured by me is at 19'-0". The system needs to be recalculated to the storage height being used or storage needs to be lowered pemanantly.
INSP-Final Inspection2/19/20072/20/20072/21/2007ACANC
DetailsTroy Cobbley
To be rescheduled since the fitter is sick today.
INSP-Final Inspection2/6/20072/7/20072/8/2007PCANC
DetailsTroy Cobbley
Per todd the canopies had to be reordered.
Sprinkler Plan Check1/11/2007 1/11/2007 DONE
PLANS/APPL TAKEN TO FRONT DESK  1/11/2007 DONE
Inspection Record Card- Fire1/11/2007 1/11/2007 DONE
Telephone call  1/11/2007 DONE
t/c w liz at DeBest Fire ###-#### - permit ready and fees given ($150.00)
Permit Ready to Issue  1/11/2007 DONE
Issue and Print Permit  1/11/2007 DONE
Telephone call  1/11/2007 DONE
Spoke with Randy Bowron and discussed the criteria for which a fire sprinkler demo permit would be required. Informed Randy that a sprinkler demo permit for the costco cooler construction project would not be required.
Application received  1/10/2007  
Pending Assignment by SAM1/10/2007