INSP-Final Inspection | 3/5/2007 | 3/5/2007 | 3/5/2007 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 3/5/2007 | 3/5/2007 | 3/5/2007 | P | PART |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 2/14/2007 | 2/15/2007 | 2/15/2007 | A | FAIL |
Troy Cobbley
|
|
|
Could not final since the ceiling tile is missing. Sprinkler piping is ok to cover.
|
INSP-Final Inspection | 1/26/2007 | 1/26/2007 | 1/26/2007 | P | PART |
Troy Cobbley
|
|
|
See the rooms marked on the approved drawings for the piping that is ok to cover. Not all of the work is complete.
|
Telephone call | | | 1/24/2007 | | DONE |
|
|
|
Called Jeff Anderson and requested hydraulic calculations to verify the addition of the new Flex head modifications. Bryan Johnson to review.
|
Sprinkler Plan Check | 1/24/2007 | | 1/24/2007 | | PASS |
|
|
|
Designer has opted not to utilize the flex head assembly for tenant modifications.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/24/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 1/24/2007 | | 1/24/2007 | | DONE |
|
|
|
|
Telephone call | | | 1/24/2007 | | DONE |
|
|
|
spoke w/ jeff anderson at provided # and he will p/u permit and pay the $150 fee
|
Permit Ready to Issue | | | 1/24/2007 | | DONE |
|
|
|
|
Issue and Print Permit | | | 1/24/2007 | | DONE |
|
|
|
|
Application received | | | 1/22/2007 | | |
|
|
|
|
Pending Assignment by SAM | 1/22/2007 | | | | |
|
|
|
|