INSP-Final Inspection | 4/12/2010 | 4/12/2010 | 4/13/2010 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
Miscellaneous action | | | 3/11/2010 | | DONE |
|
|
|
Sent email requesting project status.
|
INSP-Conference | 2/23/2007 | 2/26/2007 | 2/26/2007 | A | PASS |
Troy Cobbley
|
|
|
sprinkler piping is ok to cover
|
INSP-Sprinkler Rough-in/Hydro | 2/23/2007 | 2/23/2007 | 2/23/2007 | A | PASS |
Troy Cobbley
|
|
|
Sprinkler rough-in is passed. Insulation at the roof deck is falling on the piping/uprights and will need to be attached to the roof structur prior to a cover inspection being passed.
|
Inspection Record Card- Fire | 2/15/2007 | | 2/15/2007 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/15/2007 | | DONE |
|
|
|
|
Telephone call | | | 2/15/2007 | | DONE |
|
|
|
lft vm with mike oswalkd ###-#### that permit and fees are ready to be picked up no fee
|
CHANGE STATUS TO (ISS) | | | 2/15/2007 | | |
|
|
|
picked up plans
|
(F) Reprint permit | | | 2/15/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 2/14/2007 | | 2/14/2007 | | DONE |
|
|
|
Scope of work modified by reducucing quantity of sprinkler head modifications.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/14/2007 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/12/2007 | | |
|
|
|
|
Inspection Record Card- Fire | 2/1/2007 | | 2/1/2007 | | DONE |
|
|
|
|
Telephone call | | | 2/1/2007 | | DONE |
|
|
|
lft vm with mike oswald ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 2/1/2007 | | DONE |
|
|
|
|
Issue permit | | | 2/1/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 1/31/2007 | | 1/31/2007 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/31/2007 | | DONE |
|
|
|
|
Application received | | | 1/30/2007 | | |
|
|
|
|
Case Summary | | | 1/30/2007 | | DONE |
|
|
|
|
Pending Assignment by SAM | 1/30/2007 | | | | |
|
|
|
|