INSP-Final Inspection | 4/30/2007 | 4/30/2007 | 4/30/2007 | P | PASS |
Forrest France
|
|
|
Corrections are complete, fire sprinkler permit finaled.
|
CHANGE STATUS TO (ISS) | | | 4/30/2007 | | |
|
|
|
from rev to issue per forrest
|
Miscellaneous action | | | 4/23/2007 | | |
|
|
|
failed resubmittals/plan mod plans picked up
|
INSP-Final Inspection | 4/19/2007 | 4/20/2007 | 4/20/2007 | A | FAIL |
Forrest France
|
|
|
Provide an outside control valve as indicated on fire code review notes, also need to repair one escutcheon at the second floor atrium.
|
INSP-Sprinkler Rough-in/Hydro | 4/19/2007 | 4/19/2007 | 4/19/2007 | P | PART |
Forrest France
|
|
|
OH hydrostatic retest of the wet and antifreeze systems passed.
|
Telephone call | | | 4/19/2007 | | DONE |
|
|
|
call to lillie, permit needs to be p/u and resubmitted, left msg on voice mail.
|
INSP-Final Inspection | 4/17/2007 | 4/18/2007 | 4/18/2007 | P | FAIL |
Troy Cobbley
|
|
|
Need drawings resubmitted as previously requested. Still need the hydro test performed. Also since the anti-freeze connection point has been relocated an additional flow switch is required.
|
Plan resubmittals received | | | 4/18/2007 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 3/28/2007 | 3/30/2007 | 3/30/2007 | A | DEFR |
Forrest France
|
|
|
This is just an overhead hydro. Contact is Brian D. @ ###-####. Thank you. Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 3/22/2007 | 3/27/2007 | 3/27/2007 | P | FAIL |
Forrest France
|
|
|
OH hydrostatic test failed due to pressure loss at the guage and visible leakage at system piping, still need to provide resubmittals for changes in overhead piping.
|
INSP-Sprinkler Rough-in/Hydro | 2/26/2007 | 2/27/2007 | 2/27/2007 | A | NR |
Forrest France
|
|
|
Corrections are not yet complete for re-inspection.
|
INSP-Sprinkler Rough-in/Hydro | 2/23/2007 | 2/26/2007 | 2/26/2007 | P | PART |
Forrest France
|
|
|
UG hydrostatic test completed satisfactory.
|
INSP-Sprinkler Rough-in | 2/23/2007 | 2/26/2007 | 2/26/2007 | P | FAIL |
Forrest France
|
|
|
The installation does not match plan (mains re-routed, antifreeze supply point moved, heads deleted, DSW heads added, branch lines moved, etc.), 1st floor has overspaced and blocked heads at several locations, SW heads installed too low, 2nd floor has overspaced uprights, mixed temp. heads in the same fire area, blocked upright at the atrium, antifreeze install does not match plan, will require plan resubmittal reflecting actual installation.
|
INSP-Supply line flush | 2/23/2007 | 2/26/2007 | 2/26/2007 | P | NR |
Forrest France
|
|
|
Contact is Perly @ ###-####. Thank you Phone #: ###-####
|
Issue and Print Permit | | | 2/22/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/20/2007 | | 2/20/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/20/2007 | | DONE |
|
|
|
|
Telephone call | | | 2/20/2007 | | |
|
|
|
tlk to don weland ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 2/20/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 2/13/2007 | | 2/16/2007 | | PASS |
|
|
|
Plan review by Bryan Johnson
|
Plan resubmittals received | | | 2/13/2007 | | |
|
|
|
|
Sprinkler Plan Check | 2/5/2007 | | 2/8/2007 | | DONE |
|
|
|
plans denied by bryan Johnson
|
Miscellaneous action | | | 2/6/2007 | | DONE |
|
|
|
Early Start request approved to "install piping in truss attic system." from Shilo Automatic Sprinklers; signed-off request faxed back to them.
|
Application received | | | 2/1/2007 | | |
|
|
|
|
Pending Assignment by SAM | 2/1/2007 | | | | |
|
|
|
|