Permit Information
Permit NumberFIR07-00103
StatusFinaled
Name DEBEST FIRE PROTECTION
Site Address 1444 S ENTERTAINMENT AVE Unit: 200
Project NameANTHEM OFFICE BLDG
Customer Number 
ePlanReview 
Description
The sprinkler scope of work includes adding 162 QR heads to accommodate the new wall and ceiling layout on the second floor. The building Shell & Core is under a separate permit. The floor control valve and standpipe are also under a separate permit. The work is required to comply with the approved drawings, the plan review report, and with all applicable codes. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. This permit is attached to BLD06-03212 and Shell & Core permit FIR06-00664.
When tenant work affects fire sprinkler protection outside the permitted work area. The affected area sprinkler coverage outside the BLD permit will fall under the Fire Permit scope of work, to maintain the required fire protection within the fire sprinklered facility. The “Riser” and its supplies which include all appurtenances (including tamper, alarm and alarm monitoring) relating to the normal and correct function and integrity of this system will fall under the jurisdiction for code compliant verification.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/24/20077/26/20077/26/2007APASS
DetailsTroy Cobbley
permit finaled
INSP-Final Inspection7/24/20077/25/20077/25/2007AFAIL
DetailsTroy Cobbley
Need the shell core permit finaled first. This permit will be ready to final when that is done.
INSP-Sprinkler Rough-in/Hydro7/20/20077/20/20077/20/2007PPASS
DetailsTroy Cobbley
Hydro Test of the second floor passed.
INSP-Final Inspection7/18/20077/19/20077/19/2007PCANC
DetailsTroy Cobbley
Was to be called in when the fire alarm was ready. It wasn't
INSP-Sprinkler Rough-in7/13/20077/16/20077/16/2007APASS
DetailsTroy Cobbley
OH Cover Inspection for the stairwells and first floor corridor.
INSP-Sprinkler Rough-in7/3/20077/5/20077/5/2007APASS
DetailsTroy Cobbley
The second floor tenant improvement sprinkler piping is ok to cover. Four hangers need to be added in the Conference room to the west of the elevators. The room in the northwest corner of the building is experiencing changes and has no ceiling yet.
INSP-Sprinkler Rough-in6/26/20076/27/20076/27/2007APASS
DetailsTroy Cobbley
The two pendants in the south side soffit of the second floor elevator lobby are ok to cover
INSP-Sprinkler Rough-in6/5/20076/6/20076/7/2007PFAIL
DetailsTroy Cobbley
Rough Inspection for the 5th floor installation was ok but the plans need to be resubmitted due to riser nipples being added to the gridded system. I also inspected both standpipes except for the roof manifold and the 5th floor riser.
INSP-Supply line flush6/5/20076/7/20076/7/2007APASS
DetailsTroy Cobbley
UG flush passed
Case Summary  6/6/2007  
INSP-Sprinkler Rough-in5/29/20075/29/20075/29/2007PPASS
DetailsTroy Cobbley
The sprinkler piping located above the hardlid/closet areas are ok to cover
INSP-Sprinkler Rough-in5/24/20075/25/20075/25/2007PNR
DetailsForrest France
Work not yet completed for inspection.
FIR-Aging Inspection5/11/20075/11/20075/11/2007 NR
DetailsTroy Cobbley
Work is in progress
Issue and Print Permit  2/9/2007 DONE
PLANS/APPL TAKEN TO FRONT DESK  2/8/2007  
Inspection Record Card- Fire2/8/2007 2/8/2007 DONE
Telephone call  2/8/2007 DONE
lft ms with secretary for randy bowman ###-#### that permit and fees are ready to be picked up
Permit Ready to Issue  2/8/2007 DONE
Sprinkler Plan Check2/2/2007 2/5/2007 PASS
Plan review by Bryan Johnson
Application received  2/2/2007  
Pending Assignment by SAM2/2/2007