INSP-Final Inspection | 1/11/2008 | 1/15/2008 | 1/15/2008 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 10/9/2007 | 10/15/2007 | 10/15/2007 | A | PART |
Forrest France
|
|
|
Hydrostatic test for the 2nd and 1st floor completed areas passed, noted pending resubmittals and ordinary temp heads at the vicinity of unit heaters need to be changed.
|
INSP-Sprinkler Rough-in/Hydro | 10/9/2007 | 10/10/2007 | 10/9/2007 | A | CANC |
Forrest France
|
|
|
Phone #: ###-#### Internet Inspection Request from: Greg Kirkes Inspection to be rescheduled per conversation with contractor.
|
Issue and Print Permit | | | 7/18/2007 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/12/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/20/2007 | | 2/20/2007 | | DONE |
|
|
|
|
Miscellaneous action | | | 2/20/2007 | | DONE |
|
|
|
One set of plans is being retained for the city records. I have the 2nd set of plans to take back to Micron at next site visit. The Building plans are still under review at this time.
|
Application received | | | 2/5/2007 | | |
|
|
|
|
Pending Assignment by SAM | 2/5/2007 | | | | |
|
|
|
|
Sprinkler Plan Check | 2/20/2007 | | | | PASS |
|
|
|
Plan review by Bryan Johson (Cant release this permit until Bld Permit is picked up)
|