INSP-Final Inspection | 5/18/2007 | 5/21/2007 | 5/21/2007 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit work is approved for final, noted signage at the backflow to be installed as discussed and verified at BLD final.
|
INSP-Sprinkler Rough-in | 2/20/2007 | 2/20/2007 | 2/20/2007 | P | PASS |
Troy Cobbley
|
|
|
Sprinkler piping as installed is ok but I requested a tenting inspection prior to covering the piping. Mike is getting with the contractor to set it up next week.
|
Issue and Print Permit | | | 2/15/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 2/14/2007 | | 2/14/2007 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/14/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/14/2007 | | 2/14/2007 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/14/2007 | | DONE |
|
|
|
|
Telephone call | | | 2/14/2007 | | DONE |
|
|
|
call to mike oswald, left msg on ans mach. permit ready to p/u and fee $150
|
Case Summary | | | 2/12/2007 | | DONE |
|
|
|
|
Application received | | | 2/12/2007 | | |
|
|
|
|
Pending Assignment by SAM | 2/12/2007 | | | | |
|
|
|
|