INSP-Final Inspection | 2/13/2008 | 2/15/2008 | 2/15/2008 | A | PASS |
Forrest France
|
|
|
Painted escutcheons at two locations replaced while on site, as-built plans accepted, permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 10/25/2007 | 10/26/2007 | 10/29/2007 | P | PART |
Forrest France
|
|
|
Hydro test passed.
|
INSP-Final Inspection | 8/22/2007 | 8/23/2007 | 8/23/2007 | A | PART |
Forrest France
|
|
|
Overhead rough in is good for cover at the hard lid ceiling areas, changes to floor plan are noted.
|
INSP-Sprinkler Rough-in | 8/16/2007 | 8/17/2007 | 8/17/2007 | A | NR |
Forrest France
|
|
|
Pending light fixture obstruction issues.
|
Issue and Print Permit | | | 4/4/2007 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/2/2007 | | DONE |
|
|
|
|
Telephone call | | | 4/2/2007 | | DONE |
|
|
|
t/c w lilly at shilo ###-#### - permit ready and fees given ($150.00)
|
Inspection Record Card- Fire | 3/1/2007 | | 3/1/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 2/15/2007 | | 2/25/2007 | | PASS |
|
|
|
plans are approved as submitted by brian johnson
|
Application received | | | 2/15/2007 | | |
|
|
|
|
Pending Assignment by SAM | 2/15/2007 | | | | |
|
|
|
|