INSP-Final Inspection | 1/9/2008 | 1/10/2008 | 1/10/2008 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 10/25/2007 | 10/26/2007 | 10/29/2007 | P | PART |
Forrest France
|
|
|
Hydro test passed.
|
INSP-Final Inspection | 8/22/2007 | 8/23/2007 | 8/23/2007 | A | FAIL |
Forrest France
|
|
|
Missing sprinkler protection at one closet which exceeds dimentions allowed for coverage omission, remainder of ceilings are okay for cover.
|
INSP-Sprinkler Rough-in | 8/16/2007 | 8/17/2007 | 8/17/2007 | A | NR |
Forrest France
|
|
|
Pending light fixture obstruction issues.
|
Permit Ready to Issue | | | 5/31/2007 | | DONE |
|
|
|
|
Telephone call | | | 5/31/2007 | | DONE |
|
|
|
tlk to lilly at shilo ###-#### that permit and fees are ready to be picked up
|
Issue and Print Permit | | | 5/31/2007 | | DONE |
|
|
|
|
Meeting | | | 5/30/2007 | | DONE |
|
|
|
Meeting with Rita Deyong regarding status of attached Buidling permit, and when to issue these permits. I gave approval to issue the permit, due to the excessive length of time it is taking to get the Building plans reviewed. If there are descrepancied between the final approved building plans and those used by the sprinkler designer, it will be the responsibility of the sprinkler contractor to resubmit modified plans or if approved by the inspector, to have "as builts" on site at time of inspection.
|
Sprinkler Plan Check | 2/15/2007 | | 3/1/2007 | | PASS |
|
|
|
plans are approved as submitted by bryan johnson
note: bld. permit is being reviewed, unable to issue this permit unith the bld. permit has been issued
|
Inspection Record Card- Fire | 2/28/2007 | | 2/28/2007 | | DONE |
|
|
|
|
Application received | | | 2/15/2007 | | |
|
|
|
|
Pending Assignment by SAM | 2/15/2007 | | | | |
|
|
|
|