Agreement of Future work | 12/21/2001 | 12/21/2006 | 6/18/2007 | | DONE |
|
|
|
Upgrade Agreement to Add Sprinklers to Building Canopy 6-19-2007 Upgrade Complete.
|
INSP-Final Inspection | 6/11/2007 | 6/11/2007 | 6/11/2007 | P | PASS |
Troy Cobbley
|
|
|
Outstanding requirements completed under FIR07-00152
|
Telephone call | | | 5/8/2007 | | PART |
Bob Archibald
|
|
|
Phone conference with Mike Z. He informs me that contractor has been payed and will begin work soon. Mike will notify me of start date.
|
INSP-Final Inspection | 4/3/2007 | 4/4/2007 | 4/4/2007 | A | FAIL |
Troy Cobbley
|
|
|
The backflow needs certified and the tamper switches connected to the existing fire alarm panel.
|
INSP-Sprinkler Rough-in/Hydro | 4/3/2007 | 4/4/2007 | 4/4/2007 | A | PASS |
Troy Cobbley
|
|
|
Hydro test and rough-in passed.
|
Issue and Print Permit | | | 2/27/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/26/2007 | | 2/26/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/26/2007 | | DONE |
|
|
|
|
Telephone call | | | 2/26/2007 | | |
|
|
|
lft ms with operator for ron or brett ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 2/26/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 2/15/2007 | | 2/22/2007 | | PASS |
|
|
|
Plans are approved as submitted by Bryan Johnson
|
Case Summary | | | 2/15/2007 | | DONE |
|
|
|
|
Application received | | | 2/15/2007 | | |
|
|
|
|
Pending Assignment by SAM | 2/15/2007 | | | | |
|
|
|
|