Permit Information
Permit NumberFIR07-00163
StatusFinaled
Name DEBEST FIRE PROTECTION
Site Address 7200 W BARRISTER DR
Project NameAda County Jail Medical Unit
Customer Number 
ePlanReview 
Description
Install a new 6” underground service to supply a new riser within this fully sprinklered bldg. The bldg shall be fully sprinklered with two additional risers to be installed for future use. A double interlock pre-action system will be installed to serve through out the Detox cells. The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD06-03515.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/23/200710/24/200710/24/2007APASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection10/17/200710/23/200710/23/2007AFAIL
DetailsTroy Cobbley
One room needs the institutional heads installed, forward flush needs to be performed and a general final walk through.
INSP-Sprinkler Rough-in/Hydro10/15/200710/17/200710/17/2007PPASS
DetailsTroy Cobbley
The hydro test for the header and fdc and the preaction system passed.
INSP-Sprinkler Rough-in/Hydro10/11/200710/15/200710/15/2007APART
DetailsTroy Cobbley
OH Hydro Inspection on the three wet risers passed. The preaction hydro test failed. The riser/header and fdc still needs to be hydro tested.
INSP-Sprinkler Rough-in9/20/20079/21/20079/21/2007APASS
DetailsTroy Cobbley
The sprinkler piping above the layin ceiling tile areas are ok to cover.
INSP-Sprinkler Rough-in9/19/20079/20/20079/20/2007PCANC
DetailsTroy Cobbley
OH Cover Inspection
Phone #: ###-#### x1234 Internet Inspection Request from: Alicia Pauley Inspection cancelled from web by: Alicia Pauley
INSP-Sprinkler Rough-in8/20/20078/22/20078/22/2007PPASS
DetailsTroy Cobbley
See the city approved plans for location where the sprinkler piping is ok to cover
INSP-Sprinkler Rough-in/Hydro8/20/20078/22/20078/22/2007PPASS
DetailsTroy Cobbley
UG Hydro Test and flush passed
INSP-Sprinkler Rough-in8/15/20078/17/20078/17/2007APASS
DetailsTroy Cobbley
See the city approved plans for locations where the spirnkler piping is ok to cover. Ceilings will need to be added in the mechanical closets or the walls will need to extend to the deck. The upright will not suffice. A separation is needed between the sprinklered area and the non-sprinklered area
INSP-Sprinkler Rough-in7/26/20077/31/20077/31/2007APASS
DetailsTroy Cobbley
See the city approved plans for the areas of the medical wing that the rough-in piping is passed and other areas where the piping is ok to cover. I found one retaining strap missing and one drop that was positioned as a sprig up.
INSP-Sprinkler Rough-in/Hydro3/27/20073/28/20073/28/2007APART
DetailsForrest France
The UG fire supply line stub-in and IBR are approved for cover.
PLANS/APPL TAKEN TO FRONT DESK  3/22/2007 DONE
Inspection Record Card- Fire3/22/2007 3/22/2007 DONE
Telephone call  3/22/2007 DONE
tlk to sec ###-#### that permit and fees are ready to picked up
Permit Ready to Issue  3/22/2007  
Issue and Print Permit  3/22/2007 DONE
Sprinkler Plan Check3/9/2007 3/17/2007 PASS
Plans are approved by Bryan Johnson
Plan resubmittals received  3/9/2007  
received "4" sets of plans including each sheet of FP1 & FP2-letter of transmittal & app & "5" fire protection sub & fire sprinkler data for ada county jail -plans put on shelf
Telephone call  3/7/2007 DONE
called Debest to come pick up failed plans
Miscellaneous action  3/7/2007  
picked up failed plans
Telephone call  3/6/2007 DONE
contractor wants to pick up his denied plan sets; all plan sets taken to permit counter with a NOTE: for pick up by contractor. (BJ kept a set for his reference)
Application received  2/21/2007  
Pending Assignment by SAM2/21/2007    
Sprinkler Plan Check2/27/2007   FAIL
*Plans are denied by Bryan Johnson