Miscellaneous action | | | 6/4/2008 | | DONE |
|
|
|
Plans taken to records to scan
|
INSP-Final Inspection | 4/28/2008 | 4/28/2008 | 4/29/2008 | P | PASS |
Forrest France
|
|
|
Fire alarm permit work scope is approved for final-some locations eclipsed by subsequent tenant fire alarm modifications inspected under respective permits for the 5th and 4th floors.
|
INSP-Alarm Testing | 8/23/2007 | 8/24/2007 | 8/24/2007 | A | PART |
Forrest France
|
|
|
Re-inspection for the fire alarm work associated with the 4th floor remodel BLD07-01120 passed, remainder of alarm permit scope of work not yet completed.
|
INSP-Alarm Testing | 8/22/2007 | 8/23/2007 | 8/23/2007 | A | FAIL |
Forrest France
|
|
|
Overspaced SD at the cafeteria, strobe coverage is lacking at one area in the kitchen, audibility is too low for the kitchen service/prep area, remainder of the 4th floor west half as tested is acceptable.
|
INSP-Alarm Testing | 4/12/2007 | 4/13/2007 | 4/13/2007 | A | PART |
Forrest France
|
|
|
Testing completed for the south half of the 4th floor including one added device, pull stations at the exit stairs, SD at the service elevator, SD for stairwell fans, and retest of the telephone and electrical room detection.
|
Issue permit | | | 3/8/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/7/2007 | | 3/7/2007 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/7/2007 | | DONE |
|
|
|
|
Telephone call | | | 3/7/2007 | | DONE |
|
|
|
call to wes smith, left msg on v/m, permit ready to p/u
|
Alarm Plan Check | 3/6/2007 | | 3/6/2007 | | PASS |
|
|
|
Fire Alarm Review 2nd
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/6/2007 | | |
|
|
|
Ready for Issue
|
Plan assigned to (Mike) | 2/22/2007 | | 3/6/2007 | | PASS |
|
|
|
3/6/2007 18:55:15 MWT - activity updated through activity FIRA22 from case FIR07-00166.
|
Alarm Plan Check | 2/22/2007 | | 2/23/2007 | | FAIL |
Michael Timmerman
|
|
|
Fire Alarm Review 1st
|
Telephone call | | | 2/23/2007 | | |
|
|
|
Left Voicemail Scott Schainer ###-#### for resubmittal required
|
Miscellaneous action | | | 2/23/2007 | | |
|
|
|
Fax copy of review to Applicant, Romar Electric Wes Smith
|
Telephone call | | | 2/23/2007 | | |
|
|
|
Called Sandy ###-#### for Resubmittal
|
Telephone call | | | 2/23/2007 | | |
|
|
|
re-submittal required per mike t.
|
Application received | | | 2/22/2007 | | |
|
|
|
|
Inspection | 3/27/2007 | 3/27/2007 | | | FAIL |
|
|
|
After hours Inspection Boise Cascade Building. ( Fail)
1.) The installing contractor is using a non- approved set of floor plans for installation of fire alarm equipment on the 4th floor. The approved set of plans was found in the general contractor's office, and after review the installation was significantly different than what was on the approved set of plans.
2.) Began by testing a smoke detector outside of the Northeast stairwell, found that an alarm verification feature is programmed into the automatic fire alarm detection devices. The main FACP descriptor associated with the smoke detector had only confusing identification numbers with no association to the floor or area of the detector location.
3.) Tested another smoke detector outside of freight elevator, alarm verification was enabled on this detector also. Finally after the detector went into alarm the smoke guard doors released and another confusing descriptor displayed at the main FACP. This time the descriptor said that the alarm was at the plaza level elevator smoke detector.
4.) It was decided that a meeting needs to be set up to discuss the procedure for installation, testing and correcting problems found during inspections. Also determine why installing workers are not working from approved plans.
|