To install a life safety NFPA 13D system in a new 5317 ft/2 two story single family dwelling. This house requires a modified NFPA 13D sprinkler system. In addition to the requirements of 13D, all closets, baths and foyers shall be protected with sprinklers and attached garages shall be protected with a single row of dry sidewall sprinklers along the wall between the house and the garage. Any and all NFPA 13D systems shall be equipped with an alarm initiating device commonly referred to as a flow switch, and an outside alarm indicating device. In order to meet requirements, the system will include a booster pump as adequate supply and pressure was not available through the public water supply. All fire sprinkler work and related, which includes dual use, single service water supply, the system backflow prevention device (provided by others), shall be per NFPA 13D, approved plans, engineering/red-lining and attached review comments, under direction of the Fire Chief. This permit is attached to: BLD06-03289.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/23/20077/24/20077/24/2007APASS
DetailsForrest France
Fire sprinkler permit finaled.
INSP-Final Inspection6/13/20076/14/20076/14/2007AFAIL
DetailsForrest France
Required corrections are complete, final pending repair of a leak at one dry SW head in the garage and system pressurization.
INSP-Final Inspection6/7/20076/11/20076/11/2007AFAIL
DetailsTroy Cobbley
provide the spare heads and wrench, calc sticker, lock the valves, provide verification that the pendant head infront of the range meets the spacing requirements of nfpa 13D, provide canopy for pendant over stairs
INSP-Supply line flush5/1/20075/2/20075/2/2007PPART
DetailsForrest France
UG supply line flush completed.
INSP-Sprinkler Rough-in3/19/20073/20/20073/20/2007APART
DetailsForrest France
OH fire sprinkler install is approved for cover, all field modifications to be indicated on as-built plans.
INSP-Sprinkler Rough-in3/16/20073/19/20073/20/2007PFAIL
DetailsForrest France
OH fire sprinkler piping is still completely concealed by insulation at the entire basement floor level, proper rough-in inspection cannot be completed until work is exposed.
INSP-Sprinkler Rough-in3/15/20073/16/20073/16/2007PFAIL
DetailsTroy Cobbley
Piping on the main level has changed and heads added. As-builts will be required prior for final. Main level piping can be finished covering. The lower level piping could not be verified since all piping was buried above insulation. I notified the contractor and the builder via phone that the insulation had to come down.
PLANS/APPL TAKEN TO FRONT DESK  3/14/2007 DONE
Inspection Record Card- Fire3/14/2007 3/14/2007 DONE
Telephone call  3/14/2007 DONE
tlk to jon edes ###-#### that permit and fees are ready to be picked up
Permit Ready to Issue  3/14/2007 DONE
Issue and Print Permit  3/14/2007 DONE
Sprinkler Plan Check3/7/2007 3/12/2007 PASS
Plans are approved by Bryan Johnson
Miscellaneous action  3/7/2007 DONE
Approved Early Start request to install system.
Plan resubmittals received  3/7/2007  
Received 4 copys of sheets FP-1,FP-2 sent to fire///dld
Sprinkler Plan Check2/27/2007 3/6/2007 FAIL
Plan are denied per Bryan Johnson
Application received  2/23/2007  