Permit Information
Permit NumberFIR07-00203
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 970 W RIVER ST
Project NameIDAHO RECORDS MGMNT
Customer Number 
ePlanReview 
Description
Building D Idaho Records Management Bldg. D - To construct a new 12,745 square foot, one story addition to the east side of existing 33,000 square foot, two story storage and office building A/B. The new addition is identified as Building D. The new building addition is constructed of a pre-engineered metal building on a concrete slab floors and foundation. The fire sprinkler scope of work includes a new 8” underground service leading into the fire pump room. Two dry pipe systems will serve through out the roof and two levels on in-rack sprinklers. Rack types include single, double and multiple row.
The review comments, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to BLD06-01663.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/7/20079/7/20079/7/2007PPASS
DetailsForrest France
Corrections accepted, fire sprinkler permit finaled.
INSP-Final Inspection7/18/20077/25/20077/25/2007PFAIL
DetailsTroy Cobbley
Inspection was for the fire pump test. I noted three items that are required per NFPA 20 section 5.12. Drainage, ventilation and emergency lighting. These items were posted on a correction notice in the riser room.
INSP-Final Inspection7/18/20077/25/20077/18/2007ACANC
DetailsForrest France
PUMP TEST. PLEASE CALL JEFF PACKHAM IF THERE ARE QUESTIONS. Phone #: ###-#### Internet Inspection Request from: Jeff Packham Inspection cancelled from web by: Jeff Packham
INSP-Final Inspection7/11/20077/12/20077/12/2007APART
DetailsForrest France
Required corrections verified for completion, trip testing passed, resubmittals approved, final pending pump acceptance testing per NFPA 20.
Miscellaneous action  7/12/2007 DONE
picked up plans
INSP-Final Inspection7/10/20077/11/20077/11/2007APART
DetailsForrest France
Need curent resubmittals reflecting field modifications, remove plants blocking FDC and WPI, still need to complete trip testing, supervision and alarm tested okay.
PLANS/APPL TAKEN TO FRONT DESK  7/11/2007 DONE
Inspection Record Card- Fire7/11/2007 7/11/2007 DONE
Permit Ready to Issue  7/11/2007 DONE
Issue and Print Permit  7/11/2007 DONE
Sprinkler Plan Check7/2/2007 7/10/2007 PASS
As built Plans & Calculation are approved by Bryan Johnson
INSP-Final Inspection7/5/20077/6/20077/6/2007PFAIL
DetailsTroy Cobbley
I did not perform the pump acceptance test since the pump representative was not there as required pernfpa 20 - 14.2. Brian Johnson and dave hanniman were consulted.
INSP-Sprinkler Rough-in/Hydro7/5/20077/6/20077/6/2007PPASS
DetailsTroy Cobbley
The 24 hour air test passed.
INSP-Sprinkler Rough-in/Hydro7/5/20077/5/20077/5/2007PDEFR
DetailsForrest France
Scheduled by a contractor via Hello! on 7/5/2007 at 7:31:03 AM. Contact: ###-####.
INSP-Sprinkler Rough-in/Hydro7/3/20077/5/20077/5/2007APART
DetailsForrest France
Begin retest of the 24 hr. pneumatic for the roof level dry system at 12:30 pm with 44 1/2 psi at the guage.
INSP-Sprinkler Rough-in/Hydro7/2/20077/3/20077/3/2007ACANC
DetailsForrest France
24 hour air test for 6" dry system. Phone #: ###-#### Internet Inspection Request from: Jeff Packham
Plan resubmittals received  7/2/2007  
1 letter of transmittal,1 application,5 copys of sheets FP-1,FP-2,FP-3,FP-4 sent to Scott A.
INSP-Sprinkler Rough-in/Hydro6/27/20076/27/20076/28/2007PPART
DetailsForrest France
OH hydrostatic test completed satisfactory.
INSP-Sprinkler Rough-in/Hydro6/20/20076/21/20076/21/2007AFAIL
DetailsForrest France
The roof dry system piping failed air test due to 4psi. loss at the guage, the lower and upper mezz. system air test passed with 1/2 psi. loss. Noted items for OH rough-in including one missing head at the upper mezz. NE stairs, locaiton of the main for both upper and lower mezz. has been moved from what the approved plans indicate, plans do not reflect outside drive thru piping or system feed for the office area, noted no QOD has been installed on the dry valve trim for the system over 500 gallons, no hose connections installed at this time, plants blocking FDC and WPI will need to be removed.
INSP-Sprinkler Rough-in/Hydro6/19/20076/20/20076/20/2007APART
DetailsForrest France
Begin dry sytem air test @ 45 psi. at 11:50 am.
INSP-Sprinkler Rough-in6/19/20076/20/20076/20/2007APART
DetailsForrest France
Begin dry system air test at 45psi.
PLANS/APPL TAKEN TO FRONT DESK  3/22/2007 DONE
Inspection Record Card- Fire3/22/2007 3/22/2007 DONE
Telephone call  3/22/2007 DONE
tlk to jeff packham ###-#### that permit and fees are ready to be picked up
Permit Ready to Issue  3/22/2007 DONE
Issue and Print Permit  3/22/2007 DONE
Sprinkler Plan Check3/5/2007 3/16/2007 PASS
Plans are approved w/attached comments per Bryan Johnson
Application received  3/5/2007  
Case Summary  3/5/2007  
Plan resubmittals received  3/5/2007 DONE
permit application (4 copies), cover sheet (4 copies), Idaho records storage Building and supporting documents (4 copies) and transmittal ltr (1), FP1 of 4 (4 copies), FP2 of 4 ( 4 copies), FP3 of 4 (4 copies), FP4 of 4 (4 copies).
Plan assigned to (Scott)3/5/2007 3/5/2007 DONE
Pending Assignment by SAM3/5/2007