INSP-Final Inspection | 10/29/2007 | 10/29/2007 | 10/29/2007 | P | PASS |
Forrest France
|
|
|
Fire sprinkler final inspection passed per site visit completed by K. Roule, permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 9/21/2007 | 9/21/2007 | 9/21/2007 | P | PART |
Forrest France
|
|
|
Retest of the overhead hydrostatic for the 3rd floor wet system passed.
|
INSP-Sprinkler Rough-in/Hydro | 8/31/2007 | 9/4/2007 | 9/4/2007 | A | PART |
Forrest France
|
|
|
Hydrostatic testing for the first and second floors passed, the third floor hydro failed due to pressure loss at the guage.
|
INSP-Sprinkler Rough-in/Hydro | 8/30/2007 | 8/31/2007 | 8/31/2007 | A | PART |
Forrest France
|
|
|
The east and west standpipes and the antifreeze system all passed hydrostatic testing. Floors 1, 2 and 3 failed hydrostatic test due to visible leakage and pressure loss below 200 psi at the guages.
|
INSP-Sprinkler Rough-in | 8/21/2007 | 8/22/2007 | 8/22/2007 | A | PART |
Forrest France
|
|
|
Overhead install at the drop ceilings for the core areas on the 3rd, 2nd and 1st floors are approved for cover.
|
INSP-Sprinkler Rough-in | 7/5/2007 | 7/9/2007 | 7/9/2007 | A | PASS |
Troy Cobbley
|
|
|
The rough-in for the first floor is ok except for the sprinkler upright in the northwest corner, as marked on the plans, that is overspaced by being 7'10" off of the wall. Also there is no separation of nonsprinklered areas from the sprinklered areas as per NFPA 13 Chapter 8. I spoke to the general contractor Nick about this. It appears that he is going to install the separation instead of installing additional upright sprinklers. This will ave to be verified at the final.
|
INSP-Sprinkler Rough-in | 7/5/2007 | 7/6/2007 | 7/5/2007 | A | DEFR |
Forrest France
|
|
|
Inspection rescheduled for 7/9
|
INSP-Sprinkler Rough-in | 7/2/2007 | 7/2/2007 | 7/2/2007 | P | PART |
Forrest France
|
|
|
Rough-in inspection for the 2nd and 3rd floors completed, noted two heads exceed min. separation unless sheetrock is extended to the deck, ssu at the west stair landing does not meet req. distance from the deck, east stairway heads have not been installed at this time, noted field modifications for the 1st floor antifreeze loop to be indicated on as-built drawings, missing seismic bracing on the south antifreeze system main.
|
INSP-Sprinkler Rough-in | 6/15/2007 | 6/18/2007 | 6/18/2007 | A | PART |
Forrest France
|
|
|
Hard lid ceilings at the north entry atrium including soffits and dry sidewalls are okay for cover as noted on approved plans sheet FP3 2nd floor.
|
INSP-Sprinkler Rough-in | 6/7/2007 | 6/8/2007 | 6/8/2007 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans with todays date for the locations where the piping above the hardlids is ok to cover.
|
INSP-Supply line flush | 6/6/2007 | 6/7/2007 | 6/7/2007 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Sprinkler Rough-in | 5/29/2007 | 5/30/2007 | 5/30/2007 | A | PART |
Forrest France
|
|
|
NW stair ceiling third floor fire sprinklers are approved for cover, also discussed flange hanger attatchments for the 4" main and trapeeze assemblies.
|
INSP-Sprinkler Rough-in | 5/29/2007 | 5/29/2007 | 5/29/2007 | P | NR |
Forrest France
|
|
|
UG piping is completed, however thrust blocking is not installed at this time.
|
INSP-Sprinkler Rough-in | 5/2/2007 | 5/3/2007 | 5/3/2007 | A | PART |
Forrest France
|
|
|
OH FS is approved for cover as noted on stamped plan set.
|
INSP-Sprinkler Rough-in | 5/1/2007 | 5/2/2007 | 5/2/2007 | A | PART |
Forrest France
|
|
|
Overhead rough-in at the 1st and 2nd floor elevator lobby and restroom hard lids are good for cover as red lined on approved plans.
|
Issue and Print Permit | | | 3/22/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 3/6/2007 | | 3/21/2007 | | DONE |
|
|
|
Plans are approved by Bryan Johnson
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/21/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/21/2007 | | 3/21/2007 | | DONE |
|
|
|
|
Telephone call | | | 3/21/2007 | | DONE |
|
|
|
left vm with christopher wilson ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 3/21/2007 | | |
|
|
|
|
Application received | | | 3/6/2007 | | |
|
|
|
|
Pending Assignment by SAM | 3/6/2007 | | | | |
|
|
|
|