Permit VOIDED | 3/8/2010 | 3/8/2010 | 3/8/2010 | | DONE |
Tim Frost
|
|
|
See Miscellaneous actions dated 3/08/2010
|
Telephone call | | | 3/8/2010 | | DONE |
|
|
|
Left a message for Jim at America Fire Protection and asked him the status of the project
|
Miscellaneous action | | | 3/8/2010 | | DONE |
|
|
|
Spoke with Jim Danes. He indicated there were two building of condos A and B. The owner finished A but ran out of money for B. The underground is and inspected. The underground is drained. Apparently, the bank has repossed the property. I am voiding the permit.
|
INSP-Sprinkler Rough-in/Hydro | 5/21/2008 | 5/22/2008 | 5/22/2008 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed
|
FIR-Aging Inspection | 7/12/2007 | 7/12/2007 | 7/13/2007 | | NR |
Troy Cobbley
|
|
|
Work has not started on the project yet
|
Issue and Print Permit | | | 4/10/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/29/2007 | | 3/29/2007 | | DONE |
|
|
|
|
Telephone call | | | 3/29/2007 | | DONE |
|
|
|
tlk to jim danes ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 3/29/2007 | | |
|
|
|
|
Sprinkler Plan Check | 3/8/2007 | | 3/24/2007 | | PASS |
|
|
|
Plans are approved w/conditions
|
Case Summary | | | 3/8/2007 | | DONE |
|
|
|
|
Application received | | | 3/8/2007 | | |
|
|
|
|
Pending Assignment by SAM | 3/8/2007 | | | | |
|
|
|
|