Permit Information
Permit NumberFIR07-00235
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 1411 W GRAND AVE
Project NameGRAND AVE HOMES BLDG # 3
Customer Number 
ePlanReview 
Description
Original Scope of Work
To install a fire life safety NFPA 13R system to prevent flashover (total involvement) in the room of fire origin, where sprinklered, and to improve the chance for occupants to escape or be evacuated, in a new 9,316-ft/2 three story, apartment building. An NFPA 13R fire sprinkler protection system is required. The system shall be equipped with separate systems and controls for each unit and an alarm initiating device connected to an alarm system and an outside annunciating devise. All fire sprinkler work and related, which includes an underground water supply, the system backflow prevention device, shall be per NFPA 13R, approved plans, engineering/red-lining and attached review comments, under direction of the Fire Chief. This permit is attached to: BLD06-00076.08/30/07 Revised Scope of Work
Dry side wall heads were added to protect the balconies per IFC 903. Work is noted as Rev. 3 dated 07/25/07.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/14/20083/17/20083/17/2008APASS
DetailsForrest France
Noted corrections verified for completion, fire sprinkler permit finaled.
INSP-Final Inspection3/13/20083/14/20083/17/2008APASS
DetailsForrest France
Noted corrections verified for completion, fire sprinkler permit finaled.
INSP-Final Inspection3/12/20083/13/20083/13/2008AFAIL
DetailsForrest France
The leak at the riser supply piping has not been repaired, discovered an additional leak at a closet sprinkler head in one apartment unit, travel cap at one ssu in a mechanical closet has not been removed, one defective pendent at a stairway needs replaced, missing escutcheon at one DSW, noted two additional painted heads in need of replacement including a DSW and one pendent at a stairway. Recommend contractor to perform a complete walkthrough of the project prior to scheduling a final inspection. Re-inspection fees will apply to the next field visit for project final.
INSP-Final Inspection3/10/20083/10/20083/11/2008PFAIL
DetailsForrest France
PIV tamper switch is out of adjustment, missing orfice at inspectors test, noted leakage at the riser to be repaired, need signage at the risers indicating location of system served, missing "911" sign at the bell, permit work is not complete for final at this time.
INSP-Sprinkler Rough-in11/26/200711/27/200711/27/2007APART
DetailsForrest France
UG fire supply line flush completed okay.
INSP-Sprinkler Rough-in/Hydro11/16/200711/20/200711/20/2007PPART
DetailsForrest France
UG fire supply line hydrostatic test passed.
INSP-Sprinkler Rough-in/Hydro10/16/200710/17/200710/18/2007APASS
DetailsTroy Cobbley
Above ground hydro on Bldg 3 passed
INSP-Sprinkler Rough-in10/1/200710/3/200710/3/2007PPART
DetailsForrest France
Corrections for the overhead install are complete, tenting has been repaired, noted some heads are in close proximity to electrical junction boxes-be aware of possible fixture obstructions.
INSP-Sprinkler Rough-in/Hydro10/3/200710/3/200710/3/2007PNR
DetailsForrest France
Hydro needed, Brian F is the contact. Thank you. Phone #: ###-#### Internet Inspection Request from: Stan Beus Hydrostatic test is not ready per conversation with the fitter.
INSP-Sprinkler Rough-in9/26/20079/27/20079/27/2007APART
DetailsForrest France
Still missing tenting at the 3rd floor east apt., one head is still overspaced at the 2nd floor east unit, remainder of corrections have been completed as noted on plans, OH hydro was not ready for inspection.
INSP-Sprinkler Rough-in/Hydro9/21/20079/24/20079/24/2007PNR
DetailsForrest France
Contractor is not ready for hydrostatic testing.
INSP-Sprinkler Rough-in/Hydro9/20/20079/21/20079/21/2007AFAIL
DetailsForrest France
Some items remian to be completed on the rough-in correction notice, overhead hydro is not ready for inspection.
INSP-Sprinkler Rough-in/Hydro9/12/20079/13/20079/13/2007PFAIL
DetailsForrest France
See approved plans for locations in need of corrections including missing head at the 2nd floor system 2, overspaced head off an adjacent wall 2nd floor syst. 2, tenting at the 3rd floor is NOT adequate, hydro test failed, some DSW have been deleted, the riser and adjacent mech. room are not complete, NOTE: the 2nd floor system 1feed is not connected or has been moved and could not be located-need to verify connection point. Installation is not approved for cover.
INSP-Sprinkler Rough-in/Hydro9/10/20079/12/20079/13/2007AFAIL
DetailsForrest France
Hydrostatic test failed due to pressures below 200psi at the guage.
PLANS/APPL TAKEN TO FRONT DESK  9/7/2007 DONE
Inspection Record Card- Fire9/7/2007 9/7/2007 DONE
Telephone call  9/7/2007 DONE
tlk to lilly ###-#### that permit and fees are ready to be picked up
Permit Ready to Issue  9/7/2007  
(F) Reprint permit  9/7/2007 DONE
CHANGE STATUS TO (ISS)  9/7/2007 DONE
Sprinkler Plan Check8/21/2007 8/30/2007 PASS
Plans are approved w/attached comments per Bryan Johson
Plan resubmittals received  8/21/2007  
Pending Assignment by SAM8/21/2007 8/21/2007 DONE
Issue and Print Permit  6/25/2007 DONE
PLANS/APPL TAKEN TO FRONT DESK  6/22/2007 DONE
Inspection Record Card- Fire6/22/2007 6/22/2007 DONE
Telephone call  6/22/2007 DONE
tlk to lillie scales ###-#### that permit and fees are ready to be picked up
Permit Ready to Issue  6/22/2007 DONE
Sprinkler Plan Check6/14/2007 6/20/2007 PASS
Plans are approved w/attached comments by Bryan Johnson
Plan resubmittals received  6/14/2007  
Received 5 copies of app, water flow info, hydraulic calcs, product data, drawings on pages FP1, FP2; taken to fire review
Plan resubmittals received  5/21/2007  
Received 5 copies of application, resonse letter, copy of Boise City Plan Review, water flow info, hydraulic calcs, product data, and shop drawings on page 1; taken to fire review
Plan resubmittals received  5/1/2007  
Received five copies of the following: fire sprinkler application, letter to Bryan Johnson, Copy of Fire Plan Review, product data, water flow info, hydraulic calculations, shop drawings, page FP1; taken to fire plan review
Application received  3/15/2007  
Pending Assignment by SAM3/15/2007