INSP-Final Inspection | 5/7/2008 | 5/7/2008 | 5/7/2008 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
CHANGE STATUS TO (ISS) | | | 5/7/2008 | | DONE |
Cathy Weisshaupt
|
|
|
As per Troy, changed status to issue
|
Plan resubmittals received | | | 7/10/2007 | | |
|
|
|
Recieved application and five copies of submitall package and pages FP1 & FP2; taken to fire review
|
INSP-Sprinkler Rough-in/Hydro | 6/27/2007 | 6/28/2007 | 6/29/2007 | P | PASS |
Troy Cobbley
|
|
|
UG Flush passed
|
INSP-Supply line flush | 6/26/2007 | 6/27/2007 | 6/27/2007 | A | FAIL |
Troy Cobbley
|
|
|
UG Flush Inspection was not ready. I performed a partial sprinkler rough-in and noted deficiencies such as upright heads blocked by duct work, missing protection under stair landings and upright heads not centered between the trusses.
|
INSP-Sprinkler Rough-in | 4/23/2007 | 4/24/2007 | 4/24/2007 | P | PASS |
Troy Cobbley
|
|
|
Underground supply piping is ok to cover
|
INSP-Sprinkler Rough-in/Hydro | 3/21/2007 | 3/22/2007 | 3/22/2007 | A | PASS |
Troy Cobbley
|
|
|
The underground stub-out and 20"-0" of pipe from the stubout is ok to bury.
|
Issue and Print Permit | | | 3/20/2007 | | DONE |
|
|
|
|
Application received | | | 3/19/2007 | | |
|
|
|
|
Sprinkler Plan Check | 3/19/2007 | | 3/19/2007 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/19/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/19/2007 | | 3/19/2007 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/19/2007 | | DONE |
|
|
|
|
Telephone call | | | 3/19/2007 | | DONE |
|
|
|
call to gerald ebeling, permit ready to p/u, fee $150
|
Pending Assignment by SAM | 3/19/2007 | | | | |
|
|
|
|