INSP-Final Inspection | 11/16/2007 | 11/19/2007 | 11/19/2007 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 11/9/2007 | 11/13/2007 | 11/13/2007 | A | FAIL |
Troy Cobbley
|
|
|
Forward flush passed but the alarm portion failed
|
INSP-Final Inspection | 11/5/2007 | 11/7/2007 | 11/7/2007 | P | CANC |
Troy Cobbley
|
|
|
Todd and I agreed to reschedule for friday morning at 8:00
|
INSP-Sprinkler Rough-in/Hydro | 11/1/2007 | 11/2/2007 | 11/2/2007 | P | CANC |
Troy Cobbley
|
|
|
Overhead hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 10/25/2007 | 10/26/2007 | 10/26/2007 | A | FAIL |
Troy Cobbley
|
|
|
OH hydro test failed
|
INSP-Sprinkler Rough-in/Hydro | 10/24/2007 | 10/25/2007 | 10/25/2007 | P | FAIL |
Troy Cobbley
|
|
|
Inspection was scheduled for afternoon but due to Micron I tried to do it this morning. I found the guage below 200 psi and the fdc and the riser/header not part of the test.
|
INSP-Sprinkler Rough-in/Hydro | 9/19/2007 | 9/20/2007 | 9/20/2007 | A | PART |
Troy Cobbley
|
|
|
The first floor system passed but the upper level piping hydro test failed. Also the fire dept connection needs hydro tested.
|
INSP-Final Inspection | 9/18/2007 | 9/19/2007 | 9/19/2007 | A | CANC |
Troy Cobbley
|
|
|
Final Inspection
Phone #: ###-#### x1234 Internet Inspection Request from: Alicia Pauley Inspection cancelled from web by: Alicia Pauley
|
INSP-Sprinkler Rough-in | 8/21/2007 | 8/22/2007 | 8/22/2007 | A | PASS |
Troy Cobbley
|
|
|
OH Cover Inspection passed. Some of the upright heads still have tape on them in the warehouse area and under the stairs. I will check these at the final.
|
(F) Reprint permit | | | 7/24/2007 | | |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 7/24/2007 | | |
|
|
|
picked up plans
|
Telephone call | | | 7/23/2007 | | DONE |
|
|
|
tlk to gerald ebeling ###-#### that permit and fees (13 added) are ready to be picked up
|
Permit Ready to Issue | | | 7/23/2007 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/23/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/23/2007 | | 7/23/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 7/3/2007 | | 7/20/2007 | | PASS |
|
|
|
As-Built Plans & Calcultions are Approved by Bryan Johnson
|
INSP-Sprinkler Rough-in | 6/29/2007 | 7/2/2007 | 7/3/2007 | P | PASS |
Troy Cobbley
|
|
|
Overhead sprinkler piping is ok to cover. The trapezes need to be drilled to secure the main piping. This will be checked at the final.
|
Issue and Print Permit | | | 4/27/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 4/26/2007 | | 4/26/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/26/2007 | | DONE |
|
|
|
|
Telephone call | | | 4/26/2007 | | DONE |
|
|
|
t/c w gerald ebeling at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 4/26/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 4/11/2007 | | 4/20/2007 | | PASS |
|
|
|
plans and calculations are approved by bryan johnson
|
Application received | | | 4/11/2007 | | |
|
|
|
|
Pending Assignment by SAM | 4/11/2007 | | | | |
|
|
|
|
Inspection Record Card- Fire | 7/23/2007 | | | | |
|
|
|
|