INSP-Final Inspection | 1/30/2008 | 1/31/2008 | 1/31/2008 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in | 9/6/2007 | 9/7/2007 | 9/7/2007 | A | PASS |
Troy Cobbley
|
|
|
Some tenting modification was required but is now ok to cover
|
CHANGE STATUS TO (ISS) | | | 9/7/2007 | | |
|
|
|
issued previously
|
Inspection Record Card- Fire | 9/6/2007 | | 9/6/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/6/2007 | | |
|
|
|
|
Telephone call | | | 9/6/2007 | | DONE |
|
|
|
tlk to jim danes ###-#### that permit and no fees are ready to be picked up
|
Permit Ready to Issue | | | 9/6/2007 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 8/14/2007 | | 9/6/2007 | | PASS |
|
|
|
9/6/2007 14:56:08 CMC - activity updated through activity FIRA22 from case FIR07-00338.
|
Sprinkler Plan Check | 8/14/2007 | | 8/30/2007 | | PASS |
|
|
|
Plans are approved by Bryan Johnson
|
Plan resubmittals received | | | 8/14/2007 | | |
|
|
|
Received five binders with one application and five copies of page FP1, FP2; taken to fire review
|
INSP-Sprinkler Rough-in/Hydro | 7/31/2007 | 8/1/2007 | 8/1/2007 | A | FAIL |
Troy Cobbley
|
|
|
The plans do not match the installation. For example the riser has been relocated 15' south and two additional rooms have been added to the building which will cause the remote area to be moved to the south. The backflow device installed is not what was submitted. Additional hangers are required. The riser has been installed as cpvc and does not meet the installation requirements of cpvc installation. The plans show the riser to be sch 40 galv. Plans need to be resubmitted. I only looked at the south most building before stopping the inspection
|
Issue and Print Permit | | | 4/27/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/26/2007 | | DONE |
|
|
|
|
Telephone call | | | 4/26/2007 | | |
|
|
|
lft vm with jim danes ###-#### that permit and fees are ready to be picked up
|
Inspection Record Card- Fire | 4/26/2007 | | 4/26/2007 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/26/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 4/11/2007 | | 4/24/2007 | | PASS |
|
|
|
Plans are approved by Bryan Johnson
|
Case Summary | | | 4/11/2007 | | DONE |
|
|
|
|
Application received | | | 4/11/2007 | | |
|
|
|
|
Pending Assignment by SAM | 4/11/2007 | | | | |
|
|
|
|