INSP-Final Inspection | 11/7/2007 | 11/8/2007 | 11/9/2007 | A | PASS |
Troy Cobbley
|
|
|
Permit is ok to final per Mike Timmerman.
|
Inspection | 11/8/2007 | 11/8/2007 | 11/8/2007 | P | PASS |
|
|
|
Fire Alarm Corrections Check. Remaining 2 Items on the Medical Unit Corrections List Have Been Satisfactorly Completed. Troy Notified and Told to Final the Fire Alarm Permit.
|
INSP-Final Inspection | 10/29/2007 | 10/30/2007 | 10/31/2007 | P | FAIL |
Troy Cobbley
|
|
|
See mike timmermans notes for items tested and corrections needed.
|
Miscellaneous action | | | 10/31/2007 | | DONE |
|
|
|
Received request for fire approval for TOC from Mike Lakey emailed 10/31/07, based on latest outstanding FA issues. Request approved by D. Haneman; Fire is okay for temporary occupancy. DOC attached. Signed permit card on site, they will call for Bldg inspection tomorrow.
|
Inspection | 10/30/2007 | 10/30/2007 | 10/30/2007 | A | FAIL |
|
|
|
Inspection at Medical Unit Addition Verifying Correction Items;
1. A Duct Detector found improperly mounted in a previous inspection "Waiting Area" was changed to an In-Duct Detector. The new in-duct detector works correctly. Holes need to be patched in the duct work where old duct detector was removed.
2. The Smoke Control Sequence has changed significantly from the original proposed design. Provide a new sequence of operation and all necessary control functions and damper status at the Central Control Room FACP used as the Smoke Control Panel.
|
INSP-Final Inspection | 10/25/2007 | 10/26/2007 | 10/26/2007 | A | FAIL |
Troy Cobbley
|
|
|
The strobes now shutdown with the horns but the smoke control system still has issues. One duct smoke detector was found to be mounted incorrectly and is in the process of being fixed.
|
INSP-Alarm Testing | 10/23/2007 | 10/25/2007 | 10/26/2007 | A | FAIL |
Troy Cobbley
|
|
|
Need the smoke control system approved and the strobes to cease when the silence button is activated.
|
Inspection | 10/26/2007 | 10/26/2007 | 10/26/2007 | A | FAIL |
|
|
|
Witness Smoke Control acceptance by 3rd party engineer Jerry O'Neal, could not get desired differentials between smoke zone and corridor, while I was there. Also damper & position indication was not functional at the central control room. One duct detector needs to be relocated for proper operation.
|
INSP-Alarm Testing | 10/22/2007 | 10/25/2007 | 10/25/2007 | A | CANC |
Troy Cobbley
|
|
|
Duplicate inspection for today.
|
Inspection | 10/25/2007 | 10/25/2007 | 10/25/2007 | A | PART |
|
|
|
Inspection; Corrections to be Made From Inspection conducted on 10-25-2007
1.) Deactivate Visual Notification with Audible
2.) Witness Smoke Control Cirtification
Verify correction items found 10-23-2007 -
1.) Supervision of Future Flow & Tamper Switches in Riser Room "Complete" MWT
2.) Provide As-Built Plans with Added Devices and Address Corrections "Provided" MWT
3.) Provide additional Detector Coverage in Day Rooms to with in 21' of corners. "Devices Added OK" MWT
4.) Provide missing Smoke Detector in Room 57. " Installed" MWT
|
INSP-Alarm Testing | 10/23/2007 | 10/23/2007 | 10/23/2007 | P | FAIL |
Troy Cobbley
|
|
|
See the city approved plans for the devices tested and the deficencies found. Also still need to test a/v's
|
Alarm Plan Check | 5/30/2007 | | 5/31/2007 | | PASS |
|
|
|
Resubmittal Review
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/31/2007 | | |
|
|
|
Ready for Issue
|
Permit Ready to Issue | | | 5/31/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/31/2007 | | 5/31/2007 | | DONE |
|
|
|
|
Telephone call | | | 5/31/2007 | | DONE |
|
|
|
left vm for terry moreau permit ready to pu. no fee
|
CHANGE STATUS TO (ISS) | | | 5/31/2007 | | DONE |
|
|
|
no fee due
|
Plan assigned to (Mike) | 4/25/2007 | | 5/31/2007 | | PASS |
|
|
|
5/31/2007 10:27:50 MWT - activity updated through activity FIRA22 from case FIR07-00380.
|
Plan resubmittals received | | | 5/25/2007 | | |
|
|
|
Received application and two copies of FA1, FA2, FA3, parts list, cut sheets, wire, calculations; taken to fire review
|
Telephone call | | | 5/10/2007 | | DONE |
|
|
|
call to Terry Moreau, will p/u application for resub on mon 5/14
|
Telephone call | | | 5/10/2007 | | |
|
|
|
Called Fire Alarm Vendor, Terry Moreau, Told Terry that the Project has problems with exiting in the B Occupancy areas and Cannot be resolved without a resubmittal to the building department. I had to fail the plans
|
Miscellaneous action | | | 5/3/2007 | | |
|
|
|
Fax copy of review to fire alarm vendor, Terry Moreau, ECS
(509)-###-####
|
Telephone call | | | 5/3/2007 | | |
|
|
|
Called Architect at CSHQA John Maulin ###-#### With questions on occupancy and the detention hardware. I dont knbow how to treat this submittal as submitted.
|
Alarm Plan Check | 5/1/2007 | | 5/2/2007 | | FAIL |
|
|
|
Fire Alarm Review 1st
|
Miscellaneous action | | | 5/2/2007 | | |
|
|
|
Fax Preliminary Review to Fire Alarm Installer. We have Issues with this fire alarm plan, waiting for response from Sam.
|
Application received | | | 4/25/2007 | | |
|
|
|
|