(F) Reprint permit | | | 12/5/2016 | | DONE |
|
|
|
|
Case Summary | | | 12/5/2016 | | DONE |
|
|
|
|
INSP-Final Inspection | 8/14/2007 | 8/15/2007 | 8/15/2007 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 7/26/2007 | 7/27/2007 | 7/27/2007 | A | FAIL |
Troy Cobbley
|
|
|
See the city approved plans for corrections required. As-built plans will be needed showing the added heads.
|
INSP-Sprinkler Rough-in | 7/23/2007 | 7/23/2007 | 7/23/2007 | P | PART |
Troy Cobbley
|
|
|
The underground supply piping is ok to cover. The piping has only been buried at 4' but per the contractor the additional required 6" will be supplied by building up the ground cover. This will be verified at the sprinkler rough-in.
|
INSP-Sprinkler Rough-in | 7/19/2007 | 7/20/2007 | 7/20/2007 | A | FAIL |
Troy Cobbley
|
|
|
The inspection was for an underground cover but the contact did not answer repeated phone calls and no plans were readily available.
|
Issue and Print Permit | | | 5/30/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/25/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/25/2007 | | 5/25/2007 | | DONE |
|
|
|
|
Telephone call | | | 5/25/2007 | | DONE |
|
|
|
lft ms with tom c ###-#### that pemit and fees are ready to be picked up
|
Permit Ready to Issue | | | 5/25/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 5/7/2007 | | 5/23/2007 | | PASS |
|
|
|
Plans are approved w/condition by Bryan Johnson
|
Application received | | | 5/7/2007 | | |
|
|
|
|
Pending Assignment by SAM | 5/7/2007 | | | | |
|
|
|
|