INSP-Final Inspection | 3/28/2008 | 3/31/2008 | 3/31/2008 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. Forward flush passed.
|
INSP-Final Inspection | 3/27/2008 | 3/28/2008 | 3/28/2008 | A | CANC |
Troy Cobbley
|
|
|
Final Inspection Phone #: ###-#### x1234 Internet Inspection Request from: Alicia Pauley Inspection cancelled from web by: Alicia Pauley
|
INSP-Sprinkler Rough-in/Hydro | 2/21/2008 | 2/22/2008 | 2/22/2008 | A | PASS |
Troy Cobbley
|
|
|
Second floor hydro test passed
|
INSP-Sprinkler Rough-in/Hydro | 2/21/2008 | 2/21/2008 | 2/21/2008 | P | PASS |
Troy Cobbley
|
|
|
First floor hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 2/15/2008 | 2/19/2008 | 2/19/2008 | A | FAIL |
Troy Cobbley
|
|
|
1st floor OH Hydro test failed.
|
INSP-Sprinkler Rough-in | 2/8/2008 | 2/11/2008 | 2/11/2008 | P | PASS |
Troy Cobbley
|
|
|
The fire proof patching has been completed. Sprinkler piping is ok to cover.
|
INSP-Sprinkler Rough-in | 1/23/2008 | 1/24/2008 | 1/24/2008 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the three locations where pipin is ok to cover. These areas include the east and west entry lobbies and the east restrooms. The fire proofing has not been repaired yet above the lay-in tile areas and cannot be covered.
|
INSP-Sprinkler Rough-in | 1/21/2008 | 1/22/2008 | 1/22/2008 | A | PART |
Troy Cobbley
|
|
|
OH Cover inspection as far as the sprinkler piping installation is ok but alot of fire proofing has been damaged by all of the trades and will need to be repaired prior to the installation of the ceiling. I notified the superintendant of this.
|
INSP-Sprinkler Rough-in | 1/11/2008 | 1/11/2008 | 1/11/2008 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations where the sprinkler piping can be covered. The areas looked at today included piping above the lay in ceiling tile on the east side of the building.
|
INSP-Sprinkler Rough-in | 12/4/2007 | 12/5/2007 | 12/5/2007 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the two location in the entry vestibules where the sprinkler hangers are ok to cover.
|
INSP-Sprinkler Rough-in | 11/21/2007 | 11/26/2007 | 11/26/2007 | P | PASS |
Troy Cobbley
|
|
|
Todays inspection was for the hanger attachments that will be buried above the insulation in the north side girls and boys restrooms. The hanger attachments are ok to cover.
|
INSP-Sprinkler Rough-in | 11/15/2007 | 11/16/2007 | 11/16/2007 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for hard lid locationes where sprinkler piping is ok to cover.
|
FIR-Aging Inspection | 9/7/2007 | 9/7/2007 | 9/14/2007 | | NR |
Troy Cobbley
|
|
|
work is in progress
|
Issue and Print Permit | | | 6/8/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/6/2007 | | |
|
|
|
|
Inspection Record Card- Fire | 6/6/2007 | | 6/6/2007 | | DONE |
|
|
|
|
Telephone call | | | 6/6/2007 | | DONE |
|
|
|
lft ms with secretary for gerald ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 6/6/2007 | | |
|
|
|
|
Sprinkler Plan Check | 5/15/2007 | | 6/5/2007 | | PASS |
Sam Rogers
|
|
|
Plans are approved by Bryan Johnson
|
Application received | | | 5/15/2007 | | |
|
|
|
|
Pending Assignment by SAM | 5/15/2007 | | | | |
|
|
|
|