INSP-Final Inspection | 7/9/2007 | 7/10/2007 | 7/10/2007 | A | PASS |
Forrest France
|
|
|
Corrections verified for completion, fire sprinkler permit finaled.
|
INSP-Final Inspection | 7/6/2007 | 7/9/2007 | 7/9/2007 | A | FAIL |
Forrest France
|
|
|
Painted heads at the 2nd floor executive office will need to be replaced, one head is blocked by cabinetry, missing escutcheon at the 2nd floor south side open area.
|
INSP-Final Inspection | 6/27/2007 | 6/28/2007 | 6/28/2007 | P | PART |
Forrest France
|
|
|
Some items are completed, still missing escutcheons, one head is covered at the west first floor stairway, cash room and vault are not yet protected as indicated on approved plans.
|
INSP-Final Inspection | 6/22/2007 | 6/26/2007 | 6/26/2007 | P | NR |
Forrest France
|
|
|
Permit work is not completed for final at this time.
|
INSP-Sprinkler Rough-in | 6/22/2007 | 6/26/2007 | 6/26/2007 | P | PART |
Forrest France
|
|
|
Some items noted at previous inspection including added heads in the lobby restroom, relocated heads at the 2nd floor conference room have been completed. Remaining items include missing heads at the cash and vault rooms, missing escutcheons, one head at the teller lobby to be replaced, covered heads at the 1st floor west stair landing, still need final for the shell and core permit.
|
INSP-Final Inspection | 6/13/2007 | 6/14/2007 | 6/14/2007 | P | FAIL |
Forrest France
|
|
|
Missing heads in the womens restroom first floor, no coverage provided for the cash room and vault room, overspaced heads on the second floor at a conference room, need all ceiling tile and escutcheons in place prior to final, also need to final the shell and core permit prior to TI finals.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/12/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/12/2007 | | 6/12/2007 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/12/2007 | | DONE |
|
|
|
|
Telephone call | | | 6/12/2007 | | DONE |
|
|
|
tlk to lilly scales ###-#### that permit and no fees are ready to be picked up
|
(F) Reprint permit | | | 6/12/2007 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 6/12/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 6/4/2007 | | 6/6/2007 | | PASS |
|
|
|
Plans are approved as submitted by Bryan Johsnon
|
Plan resubmittals received | | | 6/4/2007 | | |
|
|
|
Received five copies of application, water flow info, hydraulic calcs, product data, and shop drawings on pages FP1, FP2, 3 and FP4; taken to fire review
|
INSP-Final Inspection | 5/31/2007 | 6/1/2007 | 6/1/2007 | A | FAIL |
Forrest France
|
|
|
Spacing exceeds design per calculations at several locations, one closet on the first floor will require a drop ceiling or extended walls to the deck for upright protection, no access to the front elevator lobby and restrooms due to floor finishes, installation is not approved for cover at this time.
|
Inspection Record Card- Fire | 5/31/2007 | | 5/31/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/31/2007 | | DONE |
|
|
|
|
Telephone call | | | 5/31/2007 | | DONE |
|
|
|
left vm for lilly at shilo ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 5/31/2007 | | |
|
|
|
|
Issue and Print Permit | | | 5/31/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 5/17/2007 | | 5/29/2007 | | PASS |
|
|
|
plans are approved as submitted by Bryan Johnson
|
Application received | | | 5/17/2007 | | |
|
|
|
|
Pending Assignment by SAM | 5/17/2007 | | | | |
|
|
|
|