Miscellaneous action | | | 3/11/2009 | | DONE |
|
|
|
Sent for archiving
|
INSP-Final Inspection | 1/26/2009 | 1/28/2009 | 1/28/2009 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 3/25/2008 | 3/26/2008 | 3/26/2008 | A | PASS |
Troy Cobbley
|
|
|
UG Hydro Inspection passed
|
INSP-Sprinkler Rough-in | 3/24/2008 | 3/25/2008 | 3/25/2008 | A | PASS |
Troy Cobbley
|
|
|
UG Flush Passed
|
INSP-Sprinkler Rough-in | 3/20/2008 | 3/24/2008 | 3/24/2008 | A | FAIL |
Troy Cobbley
|
|
|
This inspection was for an underground flush. The contractor had set up the flush through a 2 1/2" hose. The system riser is 4". Without a pito guage the actual flow could not be verified so no flush was performed. The underground flush shall conform to NFPA 13 10.10.2.1.3.
|
INSP-Sprinkler Rough-in | 10/30/2007 | 10/31/2007 | 10/31/2007 | A | PASS |
Troy Cobbley
|
|
|
The underground piping is ok to cover but the installation does not match the plans. Additional fitting have been added as well as additional piping. I'm contacting DeBest Fire about my concerns.
|
INSP-Sprinkler Rough-in | 7/3/2007 | 7/3/2007 | 7/3/2007 | P | PASS |
Troy Cobbley
|
|
|
5'0" underground stub out is ok to cover
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/12/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/12/2007 | | 6/12/2007 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/12/2007 | | DONE |
|
|
|
|
Telephone call | | | 6/12/2007 | | DONE |
|
|
|
tlk to jim heiller ###-#### that permit and fees are ready to be picked up
|
Issue and Print Permit | | | 6/12/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 5/21/2007 | | 6/6/2007 | | PASS |
|
|
|
Plans are approved by Bryan Johnson
|
Case Summary | | | 5/21/2007 | | DONE |
|
|
|
|
Application received | | | 5/21/2007 | | |
|
|
|
|
Pending Assignment by SAM | 5/21/2007 | | | | |
|
|
|
|