Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR07-00477
StatusFinaled
Name SIMPLEX/GRINNELL
Site Address 11875 W PRESIDENT DR
Project NameTreasure Valley Coffee
Customer Number 
ePlanReview 
Description
Scope of Work: Overhead Only
The fire sprinkler scope of work includes relocating the existing FDC to the wall outside of the existing riser location, adding a forward flow assembly and adding an additional riser to the existing manifold to serve through out the new 32,622-ft/2 warehouse addition as required. The new warehouse will be built for future Tenant space as indicated on these plans.
The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD06-02950.08/27/07 Revised Permitted Work Scope: Over Head Only
Modify the existing system by adding and relocating heads to accommodate a new wall and ceiling layout as indicated on sheet FP-2 Dated Revision 2 07-2007. Arm-overs to new head locations will be achieved utilizing mechanical tees. This review is limited to the interior of the project as outlined on sheet FP-2 @ Col. B & D, 11-9. Total # of heads affected is 25.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/30/200710/31/200710/31/2007APASS
DetailsTroy Cobbley
permit finaled
CHANGE STATUS TO (ISS)  10/30/2007 DONE
reopen flow switch was not hooked to the fire panel needs to be reopened
INSP-Final Inspection10/5/200710/8/200710/8/2007APASS
DetailsTroy Cobbley
The hydro test on the new system passed and the overhead inspection passed except in the existing area/expansion needs three additional heads due to overspacing off of the wall.
INSP-Final Inspection10/1/200710/5/200710/5/2007AFAIL
DetailsTroy Cobbley
The hydro test above the check valve held pressure but between the check valve and the fdc did not hold pressure
Issue and Print Permit  9/10/2007 DONE
PLANS/APPL TAKEN TO FRONT DESK  9/7/2007 DONE
Inspection Record Card- Fire9/7/2007 9/7/2007 DONE
Telephone call  9/7/2007 DONE
tlk to brad bettencourt ###-#### that permit and fees are ready to be picked up
Permit Ready to Issue  9/7/2007 DONE
Sprinkler Plan Check8/13/2007 8/27/2007 PASS
Plans are approved by Bryan Johnson
Plan resubmittals received  8/13/2007  
INSP-Sprinkler Rough-in8/6/20078/6/20078/6/2007PFAIL
DetailsTroy Cobbley
I inspected the two bays over the mezzanine and found that the hangers and trapeze members are the wrong size. This is the only area I inspected.
INSP-Sprinkler Rough-in8/1/20078/2/20078/3/2007PPASS
DetailsTroy Cobbley
This inspection was for the hanger attachment points that will soon be covered with insulation. The hanger attachments passed.
PLANS/APPL TAKEN TO FRONT DESK  6/29/2007  
Inspection Record Card- Fire6/19/2007 6/29/2007 DONE
Telephone call  6/29/2007 DONE
tlk to brad bettencourt ###-#### that permit and -0- are ready to be picked up
Permit Ready to Issue  6/29/2007 DONE
CHANGE STATUS TO (ISS)  6/29/2007  
already issued previously
(F) Reprint permit  6/29/2007  
Sprinkler Plan Check6/19/2007 6/26/2007 PASS
Revised Plans are approved by Bryan Johnson
Plan resubmittals received  6/19/2007  
PLANS/APPL TAKEN TO FRONT DESK  6/15/2007 DONE
Override - Parcel Holds  6/15/2007  
Inspection Record Card- Fire6/15/2007 6/15/2007 DONE
Override - Parcel Holds  6/15/2007  
Inspection Record Card- Fire6/15/2007 6/15/2007 DONE
Telephone call  6/15/2007 DONE
tlk to brad bettencourt ###-#### that permit and fees are ready to be picked up
Override - Parcel Holds  6/15/2007  
Permit Ready to Issue  6/15/2007 DONE
Override - Parcel Holds  6/15/2007  
Issue and Print Permit  6/15/2007  
Sprinkler Plan Check5/24/2007 6/12/2007 PASS
Plans are approved with conditions per Bryan Johnson
Case Summary  5/24/2007 DONE
Application received  5/24/2007  
Pending Assignment by SAM5/24/2007    
Pending Assignment by SAM8/13/2007