Information based on query as of Friday, August 16, 2024.
Permit Information
Permit NumberFIR07-00482
StatusFinaled
Name AMERICAN FIRE PROTECTION LLC
Site Address 222 S BROADWAY AVE
Project Name 
Customer Number 
ePlanReview 
Description
Scope of Work
Modify the existing system. The work includes adding a wet riser to serve the 2nd, 3rd and 4th floors. On the first floor, cap the existing supply’s to the upper floors. This will separate the first floor. Provide new floor control to the 2nd - 4th floors. Nun a new 2.5” supply loop on the first floor to feed the upper floors. In addition, all of the existing head on the 1st through 4th floors will be changed out to QR. All fire sprinkler work and related shall be performed per NFPA 13, approved plans, engineering/red-lining and attached review comments, under direction of the Fire Chief. This permit is not attached to any other permit.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/10/20083/10/20083/11/2008APASS
DetailsForrest France
Fire sprinkler permit finaled.
INSP-Sprinkler Rough-in/Hydro11/2/200711/5/200711/5/2007PPART
DetailsForrest France
OH hydrostatic testing passed.
INSP-Final Inspection8/10/20078/16/20078/16/2007PNR
DetailsForrest France
Need completion of the OH hydrostatic tests and related riser supervision testing prior to final.
INSP-Sprinkler Rough-in/Hydro8/10/20078/16/20078/16/2007PPART
DetailsForrest France
Verified corrections noted at the previous inspection have been completed, hydrostatic testing failed due to pressures below 200 psi at the guages.
INSP-Sprinkler Rough-in/Hydro8/7/20078/10/20078/10/2007PDEFR
DetailsForrest France
Rescheduled per discussion with contractor.
INSP-Final Inspection8/7/20078/10/20078/10/2007PNR
DetailsForrest France
Need to test sprinkler monitoring and alarm via project related FA permit prior to final approval.
INSP-Sprinkler Rough-in/Hydro7/27/20077/30/20077/31/2007PFAIL
DetailsForrest France
Provide longitudinal bracing for the 2.5" main as discussed, need to fire caulk new penetrations in existing rated walls, need to install intermediate temp. heads at the stairway skylights.
PLANS/APPL TAKEN TO FRONT DESK  6/20/2007 DONE
Inspection Record Card- Fire6/20/2007 6/20/2007 DONE
Permit Ready to Issue  6/20/2007 DONE
Telephone call  6/20/2007 DONE
tlk to jim danes ###-#### that permit and fees are ready to be picked up
Issue permit  6/20/2007 DONE
Sprinkler Plan Check5/25/2007 6/18/2007 PASS
Plans are approved by bryan johnson
Case Summary  5/25/2007 DONE
Application received  5/25/2007  
Pending Assignment by SAM5/25/2007