INSP-Final Inspection | 8/13/2007 | 8/13/2007 | 8/13/2007 | P | PASS |
Forrest France
|
|
|
Fire sprinkler final inspection passed, permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 6/19/2007 | 6/19/2007 | 6/19/2007 | P | PART |
Forrest France
|
|
|
Approved dry system modifications for cover, noted four plugged tees which will need reconfigured to avoid water collection and freeze potential.
|
Inspection Record Card- Fire | 6/18/2007 | | 6/18/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/18/2007 | | DONE |
|
|
|
|
Telephone call | | | 6/18/2007 | | |
|
|
|
lft vm with keith dilworth ###-#### that permit and fees are ready to be ready
|
Permit Ready to Issue | | | 6/18/2007 | | |
|
|
|
|
Issue and Print Permit | | | 6/18/2007 | | |
|
|
|
|
Sprinkler Plan Check | 6/1/2007 | | 6/14/2007 | | PASS |
|
|
|
Plans are approved by Bryan Johnson
|
Telephone call | | | 6/1/2007 | | DONE |
|
|
|
telcon from Keith at Debest to discuss need for an Early Start approval to coordinate with construction work to add a new section of ceiling in parking garage. He will fax a request later today.
|
Miscellaneous action | | | 6/1/2007 | | DONE |
|
|
|
Request for Early Start approved subject to conditions as noted in request and as annotated: Must call for rough-in inspection prior to installation of ceiling tile.
|
Application received | | | 5/30/2007 | | |
|
|
|
|
Pending Assignment by SAM | 5/30/2007 | | | | |
|
|
|
|