INSP-Final Inspection | 8/17/2007 | 8/20/2007 | 8/20/2007 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 8/13/2007 | 8/14/2007 | 8/14/2007 | P | FAIL |
Troy Cobbley
|
|
|
See the front sheet of the city approved plans for the items that need correcting.
|
Telephone call | | | 8/3/2007 | | DONE |
|
|
|
telcon from JAckie Phelps, CM re expediting insepctions to meet opeing date of 8/22. I indicated we are now able to assist with additional inspectors on some occassions if they give us some notice to plan. In this case, they are only at rough in stage and sprinkler contractor called for inspection without approved plans reflecting their field modifications; those plans were resubmitted the day after the rough-in. We cannot do patial or limited area inspections unless they have approved plans on which we can annotate the areas inspected. The most important action she can take is to ensure contractors do not call for inspections unless they have approved plans for what they installed or they have followed the published procedures for Field Approval of plan modifications.
|
Issue and Print Permit | | | 6/7/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/5/2007 | | 6/5/2007 | | DONE |
|
|
|
|
Telephone call | | | 6/5/2007 | | DONE |
|
|
|
left vm for charlie bayne at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 6/5/2007 | | |
|
|
|
|
Plan assigned to (Mike) | 5/30/2007 | | 6/4/2007 | | PASS |
|
|
|
6/4/2007 15:47:58 MWT - activity updated through activity FIRA22 from case FIR07-00490.
|
Alarm Plan Check | 6/4/2007 | | 6/4/2007 | | PASS |
|
|
|
Fire Alarm Review 1st
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/4/2007 | | |
|
|
|
Ready for Issue
|
Application received | | | 5/30/2007 | | |
|
|
|
|