FIR-Aging Inspection | 6/14/2010 | 6/14/2010 | 6/16/2010 | | DONE |
Forrest France
|
|
|
Met with general contractor on site, final scheduled, inspection passed.
|
INSP-Final Inspection | 6/15/2010 | 6/16/2010 | 6/16/2010 | A | PASS |
Forrest France
|
|
|
Final walkthrough completed satisfactory, fire sprinkler permit finaled.
|
Miscellaneous action | | | 3/11/2010 | | DONE |
|
|
|
Sent email requesting project status.
|
INSP-Final Inspection | 12/8/2008 | 12/8/2008 | 12/8/2008 | P | PART |
Forrest France
|
|
|
Okay for final when ceilings are finished.
|
INSP-Final Inspection | 9/3/2008 | 9/3/2008 | 9/3/2008 | P | PART |
Forrest France
|
|
|
Final pending ceilings and escutcheons.
|
FIR-Aging Inspection | 12/5/2007 | 12/5/2007 | 12/5/2007 | | DEFR |
Forrest France
|
|
|
Phone call to contractor regarding project status, work is in progress, inspection pending.
|
Sprinkler Plan Check | 6/5/2007 | | 6/5/2007 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/5/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/5/2007 | | 6/5/2007 | | DONE |
|
|
|
|
Telephone call | | | 6/5/2007 | | DONE |
|
|
|
t/c w brodie at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 6/5/2007 | | |
|
|
|
|
Issue and Print Permit | | | 6/5/2007 | | DONE |
|
|
|
|
Application received | | | 6/1/2007 | | |
|
|
|
|