INSP-Final Inspection | 8/11/2008 | 8/11/2008 | 8/11/2008 | A | PASS |
Forrest France
|
|
|
UG fire supply line permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 5/1/2008 | 5/2/2008 | 5/2/2008 | P | PART |
Forrest France
|
|
|
UG fire supply line and remote FDC piping passed hydrostatic testing.
|
INSP-Supply line flush | 4/1/2008 | 4/4/2008 | 4/4/2008 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed.
|
INSP-Supply line flush | 3/27/2008 | 3/28/2008 | 3/28/2008 | A | CANC |
Troy Cobbley
|
|
|
Per Richard they are having a problem corrdinating with United Water. Inspection will be rescheduled.
|
INSP-Sprinkler Rough-in | 7/11/2007 | 7/12/2007 | 7/12/2007 | A | PART |
Forrest France
|
|
|
FDC pit and drain are approved.
|
INSP-Sprinkler Rough-in | 7/9/2007 | 7/10/2007 | 7/10/2007 | A | PART |
Troy Cobbley
|
|
|
The underground is ok to cover except for the vault/access at the remote FDC has not been installed nor has the auxillary drain or the ball drip or even the drainage field. I contacted Stan Beus about this. He stated these items would be called in for inspection.
|
Sprinkler Plan Check | 6/6/2007 | | 6/26/2007 | | PASS |
|
|
|
Plan are approved underground by Bryan Johnson
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/26/2007 | | |
|
|
|
|
Inspection Record Card- Fire | 6/26/2007 | | 6/26/2007 | | DONE |
|
|
|
|
Telephone call | | | 6/26/2007 | | DONE |
|
|
|
tlk to lilly scales ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 6/26/2007 | | DONE |
|
|
|
|
Issue and Print Permit | | | 6/26/2007 | | DONE |
|
|
|
|
Application received | | | 6/6/2007 | | |
|
|
|
|
Pending Assignment by SAM | 6/6/2007 | | | | |
|
|
|
|