INSP-Final Inspection | 7/12/2007 | 7/12/2007 | 7/12/2007 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. An earthquake brace still needs to be installed on the new sprig up. This will be checked at the building final.
|
INSP-Sprinkler Rough-in | 7/10/2007 | 7/10/2007 | 7/10/2007 | P | PART |
Troy Cobbley
|
|
|
The sprinkler piping in the retail area can be covered but one upright sprinkler head in the stockroom is overspaced and an existing hanger for piping along the stockroom wall has been disconnected from the roof deck.
|
Sprinkler Plan Check | 6/18/2007 | | 6/18/2007 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/18/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/18/2007 | | 6/18/2007 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/18/2007 | | |
|
|
|
|
Telephone call | | | 6/18/2007 | | DONE |
|
|
|
t/c w brodie at TVFP ###-#### - permit ready and fees given
|
Issue and Print Permit | | | 6/18/2007 | | DONE |
|
|
|
|
Application received | | | 6/14/2007 | | |
|
|
|
|
Pending Assignment by SAM | 6/14/2007 | | | | |
|
|
|
|