INSP-Final Inspection | 8/28/2007 | 8/28/2007 | 8/28/2007 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 8/8/2007 | 8/8/2007 | 8/8/2007 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given until the flow switch and tamper switch have been connected to the fire alarm panel. Also an additional emergency light is required in the stairway. Once this is done the permit can be finaled.
|
INSP-Sprinkler Rough-in | 8/7/2007 | 8/8/2007 | 8/8/2007 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given until the flow switch and tamper switch have been connected to the fire alarm panel. Once this is done the permit can be finaled.
|
INSP-Sprinkler Rough-in/Hydro | 8/3/2007 | 8/6/2007 | 8/6/2007 | A | FAIL |
Troy Cobbley
|
|
|
No approved plans on site and the ceiling tile has been installed.
|
Issue and Print Permit | | | 8/3/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/1/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/1/2007 | | 8/1/2007 | | DONE |
|
|
|
|
Telephone call | | | 8/1/2007 | | DONE |
|
|
|
lft ms with operator ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 8/1/2007 | | |
|
|
|
|
Sprinkler Plan Check | 8/1/2007 | | 7/30/2007 | | PASS |
|
|
|
Plans are approved by Bryan Johnson
|
Plan resubmittals received | | | 7/26/2007 | | |
|
|
|
|
Sprinkler Plan Check | | | 7/6/2007 | | FAIL |
|
|
|
REv. by BJ. These plans were denied due to lack of detail and existing system information. Upon request, the denied set may be retrieved from our office for salvage. denied plans will be stored for five working days
|
Case Summary | | | 6/15/2007 | | |
|
|
|
|
Application received | | | 6/15/2007 | | |
|
|
|
|
Pending Assignment by SAM | 6/15/2007 | | | | |
|
|
|
|