INSP-Final Inspection | 12/20/2007 | 12/20/2007 | 12/20/2007 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 12/4/2007 | 12/5/2007 | 12/5/2007 | A | PASS |
Troy Cobbley
|
|
|
OH Hydro Inspection passed
|
INSP-Sprinkler Rough-in/Hydro | 12/3/2007 | 12/4/2007 | 12/4/2007 | P | CANC |
Troy Cobbley
|
|
|
OH Hydro Inspection needs rescheduled due to time constraints.
|
INSP-Sprinkler Rough-in/Hydro | 11/28/2007 | 11/29/2007 | 11/29/2007 | A | FAIL |
Troy Cobbley
|
|
|
OH Hydro failed
|
INSP-Sprinkler Rough-in/Hydro | 10/30/2007 | 10/31/2007 | 10/31/2007 | A | FAIL |
Troy Cobbley
|
|
|
Overhead hydro failed due to loss of pressure and the fdc not being tested.
|
INSP-Supply line flush | 10/3/2007 | 10/4/2007 | 10/4/2007 | A | PASS |
Troy Cobbley
|
|
|
UG Flush passed
|
INSP-Sprinkler Rough-in | 9/26/2007 | 9/27/2007 | 9/27/2007 | A | PASS |
Troy Cobbley
|
|
|
The spirnkler piping is ok to cover.
|
INSP-Sprinkler Rough-in | 9/26/2007 | 9/26/2007 | 9/27/2007 | P | FAIL |
Troy Cobbley
|
|
|
The tenting of the sprinkler piping is not complete.
|
INSP-Sprinkler Rough-in | 9/21/2007 | 9/24/2007 | 9/24/2007 | A | FAIL |
Troy Cobbley
|
|
|
Work was not complete. Also the dry sidewall heads at the patios need to be reaised or the underside of the deck above lowered.
|
INSP-Sprinkler Rough-in | 9/19/2007 | 9/20/2007 | 9/20/2007 | A | CANC |
Troy Cobbley
|
|
|
See yesterdays inspection comments.
|
INSP-Sprinkler Rough-in | 9/18/2007 | 9/19/2007 | 9/19/2007 | A | CANC |
Troy Cobbley
|
|
|
This project not inspected due to contractor wanting to make a determination on obstructions due to issues found at FIR07-00586. It will be rescheduled when a decision is made.
|
Telephone call | | | 9/7/2007 | | DONE |
|
|
|
tlk to shawn ramsey ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 9/7/2007 | | DONE |
|
|
|
|
Issue and Print Permit | | | 9/7/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/6/2007 | | |
|
|
|
|
Inspection Record Card- Fire | 9/6/2007 | | 9/6/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 8/27/2007 | | 9/4/2007 | | PASS |
|
|
|
Plans are approved by Bryan Johnson
|
Plan resubmittals received | | | 8/27/2007 | | |
|
|
|
received 1 application, 5 index for fire protection submittals,and 5 plans (sheets 1 OF 2 ) sent to fire Scott A.
|
Plan resubmittals received | | | 8/1/2007 | | |
|
|
|
received 1 application, 5 index for fire protection submittals,and 5 plans (sheets 1 OF 2 ) sent to fire Scott A.
|
Application received | | | 7/3/2007 | | |
|
|
|
|
Pending Assignment by SAM | 7/3/2007 | | | | |
|
|
|
|