INSP-Final Inspection | 12/20/2007 | 12/20/2007 | 12/20/2007 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 12/6/2007 | 12/7/2007 | 12/7/2007 | A | PASS |
Troy Cobbley
|
|
|
OH Hydro Inspection passed
|
INSP-Sprinkler Rough-in/Hydro | 12/4/2007 | 12/5/2007 | 12/5/2007 | A | FAIL |
Troy Cobbley
|
|
|
Overhead hydro test failed
|
INSP-Sprinkler Rough-in/Hydro | 12/3/2007 | 12/4/2007 | 12/4/2007 | P | CANC |
Troy Cobbley
|
|
|
OH Hydro Inspection needs rescheduled due to time constraints.
|
INSP-Sprinkler Rough-in/Hydro | 11/28/2007 | 11/29/2007 | 11/29/2007 | A | FAIL |
Troy Cobbley
|
|
|
OH Hydro failed
|
INSP-Sprinkler Rough-in/Hydro | 10/30/2007 | 10/31/2007 | 10/31/2007 | A | FAIL |
Troy Cobbley
|
|
|
Overhead hydro failed due to loss of pressure and the fdc not being tested.
|
INSP-Supply line flush | 10/3/2007 | 10/4/2007 | 10/4/2007 | A | PASS |
Troy Cobbley
|
|
|
UG Flush passed
|
INSP-Sprinkler Rough-in | 9/26/2007 | 9/27/2007 | 9/27/2007 | A | PASS |
Troy Cobbley
|
|
|
The spirnkler piping is ok to cover.
|
INSP-Sprinkler Rough-in | 9/21/2007 | 9/24/2007 | 9/24/2007 | A | PASS |
Troy Cobbley
|
|
|
The sprinkler piping is ok to cover. The general contractor agreed to provide pictures of the insulation to be placed behind the dry sidewall heads. Also the dry sidewall heads at the patios need to be reaised or the underside of the deck above lowered.
|
INSP-Sprinkler Rough-in | 9/19/2007 | 9/20/2007 | 9/20/2007 | A | CANC |
Troy Cobbley
|
|
|
See yesterdays inspection comments.
|
INSP-Sprinkler Rough-in | 9/18/2007 | 9/19/2007 | 9/19/2007 | A | CANC |
Troy Cobbley
|
|
|
This project not inspected due to contractor wanting to make a determination on obstructions due to issues found at FIR07-00586. It will be rescheduled when a decision is made.
|
Telephone call | | | 9/12/2007 | | |
|
|
|
tlk to shawn 3221511 that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 9/12/2007 | | DONE |
|
|
|
|
Issue and Print Permit | | | 9/12/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/10/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 9/10/2007 | | 9/10/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 8/27/2007 | | 9/5/2007 | | PASS |
|
|
|
Plans are approved by bryan Johnson
|
Plan resubmittals received | | | 8/27/2007 | | |
|
|
|
received 1 application, 5 index for fire protection submittals,and 5 plans (sheets 1 OF 2 ) sent to fire Scott A.
|
Plan resubmittals received | | | 8/1/2007 | | |
|
|
|
received 1 application, 5 index for fire protection submittals,and 5 plans (sheets 1 OF 2 ) sent to fire Scott A.
|
Application received | | | 7/3/2007 | | |
|
|
|
|
Pending Assignment by SAM | 7/3/2007 | | | | |
|
|
|
|