INSP-Final Inspection | 8/22/2007 | 8/22/2007 | 8/22/2007 | P | PASS |
Forrest France
|
|
|
Required corrections are complete, final fire sprinkler permit work inspection passed.
|
INSP-Final Inspection | 8/20/2007 | 8/21/2007 | 8/21/2007 | P | FAIL |
Forrest France
|
|
|
The permit card, review notes, approved plan documents and inspection record paperwork are to be on site at all times for verification of code compliance at the time of field inspection per conditon of the permit.
|
INSP-Final Inspection | 8/17/2007 | 8/17/2007 | 8/17/2007 | P | DEFR |
Forrest France
|
|
|
Scheduled by a contractor via Hello! on 8/17/2007 at 9:37:00 AM. Contact: ###-#### Overbooked, no time available to complete this inspection today, to be rescheduled as discussed with contractor.
|
Sprinkler Plan Check | 7/10/2007 | | 7/10/2007 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/10/2007 | | DONE |
|
|
|
|
Plan resubmittals received | | | 7/10/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/10/2007 | | 7/10/2007 | | DONE |
|
|
|
|
Issue and Print Permit | | | 7/10/2007 | | DONE |
|
|
|
|
Telephone call | | | 7/5/2007 | | DONE |
|
|
|
lft message with delta fire for dave gates ###-#### that permit has been failed
|
Application received | | | 7/3/2007 | | |
|
|
|
|
Sprinkler Plan Check | 7/3/2007 | | 7/3/2007 | | FAIL |
|
|
|
Faxed resubmittal items to designer/applicant.
NFPA 13-11.2.2.8.2 When backflow prevention valves are installed on pipe schedule systems, the friction losses of the device shall be accounted for when determining acceptable residual pressure at the top level of sprinklers. The friction loss of this device [in psi (bar)] shall be added to the elevation loss and the residual pressure at the top row of sprinklers to determine the total pressure needed at the water supply.
*Please resubmit calculations verifying the above requirement.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/3/2007 | | |
|
|
|
|
Pending Assignment by SAM | 7/3/2007 | | | | |
|
|
|
|