INSP-Final Inspection | 7/28/2008 | 7/28/2008 | 7/28/2008 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Supply line flush | 9/21/2007 | 9/24/2007 | 9/24/2007 | P | PART |
Forrest France
|
|
|
UG fire supply line flush completed satisfactory.
|
INSP-Sprinkler Rough-in | 8/21/2007 | 8/21/2007 | 8/22/2007 | P | PASS |
Troy Cobbley
|
|
|
The remaining portion of underground supply is ok to cover. Needs hydro tested and flushed.
|
INSP-Sprinkler Rough-in | 7/12/2007 | 7/12/2007 | 7/13/2007 | P | PASS |
Troy Cobbley
|
|
|
The underground supply piping from the building out approximately 20' is ok to cover. See the city approved plans for the piping reroute around the building footing. I asked Stan to have his office show this change on the overhead submittals so that it is included in the hydraulic calculations.
|
Sprinkler Plan Check | 7/10/2007 | | 7/10/2007 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/10/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/10/2007 | | 7/10/2007 | | DONE |
|
|
|
|
Telephone call | | | 7/10/2007 | | DONE |
|
|
|
spoke w/ lillie and informed of fees and permit ready
|
Permit Ready to Issue | | | 7/10/2007 | | DONE |
|
|
|
|
Issue and Print Permit | | | 7/10/2007 | | DONE |
|
|
|
|
Application received | | | 7/6/2007 | | |
|
|
|
|
Pending Assignment by SAM | 7/6/2007 | | | | |
|
|
|
|