INSP-Final Inspection | 9/28/2007 | 10/1/2007 | 10/1/2007 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 9/26/2007 | 9/27/2007 | 9/27/2007 | A | CANC |
Troy Cobbley
|
|
|
Canceled per mike Phone #: ###-####
|
INSP-Sprinkler Rough-in | 9/12/2007 | 9/12/2007 | 9/13/2007 | P | CANC |
Troy Cobbley
|
|
|
The second floor piping can be covered. A sprinkler head needs to be added in the small triangular closet in the reception area.
|
INSP-Sprinkler Rough-in | 9/10/2007 | 9/10/2007 | 9/11/2007 | P | FAIL |
Troy Cobbley
|
|
|
This permit will be ok to final when the shell permit is passed. It is waiting for permanant heat.
|
Issue permit | | | 8/6/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/2/2007 | | DONE |
|
|
|
|
Telephone call | | | 8/2/2007 | | DONE |
|
|
|
tlk to greg johnson ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 8/2/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/2/2007 | | 8/2/2007 | | DONE |
|
|
|
|
Telephone call | | | 8/1/2007 | | DONE |
|
|
|
The fire marshal has determined the fire sprinkler floor control valve assemblies, (referenced in IFC review comments for BLD07-01452), for the tenant improvement project FIR07-00602, 1st American Title, shall not be required.
|
Sprinkler Plan Check | 7/11/2007 | | 8/1/2007 | | PASS |
|
|
|
Plans are approved by Bryan Johnson
|
Application received | | | 7/11/2007 | | |
|
|
|
|