INSP-Final Inspection | 9/24/2007 | 9/24/2007 | 9/24/2007 | P | PASS |
Forrest France
|
|
|
Fire sprinkler passed final inspection, permit finaled.
|
INSP-Sprinkler Rough-in | 9/19/2007 | 9/20/2007 | 9/20/2007 | A | PART |
Forrest France
|
|
|
Remainder of the overhead rough-in is approved for cover as noted on stamped plan set.
|
INSP-Sprinkler Rough-in | 9/19/2007 | 9/19/2007 | 9/20/2007 | P | CANC |
Forrest France
|
|
|
Overbooked.
|
INSP-Sprinkler Rough-in | 9/11/2007 | 9/12/2007 | 9/12/2007 | A | PART |
Forrest France
|
|
|
See approved plans for areas okay for cover at the hard lid ceilings.
|
INSP-Sprinkler Rough-in | 8/29/2007 | 8/30/2007 | 8/30/2007 | A | PART |
Forrest France
|
|
|
Required corrections noted at the previous inspection have been repaired, OH fire sprinkler modifications for phase one as noted on approved plans are okay for ceiling cover.
|
INSP-Sprinkler Rough-in | 8/29/2007 | 8/29/2007 | 8/29/2007 | P | CANC |
Troy Cobbley
|
|
|
Due to the abundance of inspections today there was not adequate time to perform this one. It will need to be rescheduled.
|
INSP-Sprinkler Rough-in | 8/22/2007 | 8/23/2007 | 8/23/2007 | A | FAIL |
Forrest France
|
|
|
See approved plans for areas inspected and noted defficiences including overspaced heads at an office and equip. room, missing hangers at two arm-overs, and missing heads at three closets.
|
Issue and Print Permit | | | 8/22/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/18/2007 | | 7/18/2007 | | DONE |
|
|
|
|
Telephone call | | | 7/18/2007 | | DONE |
|
|
|
tlk to trent bice at ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 7/18/2007 | | DONE |
|
|
|
|
Application received | | | 7/17/2007 | | DONE |
|
|
|
Plans were dropped off on 6/28/07 at the FD instead of in PDS. I located the plans today after Michelle of Phoenix FP called to inquire about status of review. She had been misdirected by the 1st flr lobby counter staff to the FD; the FD mistakenly accepted the plans and routed them to Mark Sentino, where they were finally located. Will expedite this review.
|
Sprinkler Plan Check | 6/28/2007 | | 7/17/2007 | | PASS |
|
|
|
Plans approved as drawn, subject to field verification by the Fire inspector.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/17/2007 | | DONE |
|
|
|
|
Pending Assignment by SAM | 7/17/2007 | | | | |
|
|
|
|