Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR07-00661
StatusFinaled
Name IDAHO FIRE PROTECTION
Site Address 800 W IDAHO ST
Project NameTHE MODE BUILDING
Customer Number 
ePlanReview 
Description
The Permitted Work Scope: Over Head Only
Modify the existing system by relocating heads to accommodate a new ceiling layout in on the third floor. Three new heads will be added at the second level where the escalator was removed.
The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to BLD07-00898 & Demo permit FIR07-00613. When tenant work affects fire sprinkler protection outside the permitted work area due to the installation of tenant-demising or new partition walls, the affected area sprinkler coverage outside the BLD permit will fall under the Fire Permit scope of work, to maintain the required fire protection within the fire sprinklered facility. The “Riser” and its supplies which include all appurtenances (including tamper, alarm and alarm monitoring) relating to the normal and correct function and integrity of this system will fall under the jurisdiction for code compliant verification.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/28/200711/28/200711/28/2007APASS
DetailsForrest France
Final inspection passed, field modifications are approved, permit finaled.
INSP-Sprinkler Rough-in/Hydro11/8/200711/8/200711/8/2007PPART
DetailsForrest France
Work completed is outside this permit scope, notified contractor to obtain a quick permit for the six relcoated heads at the first floor hallway.
INSP-Sprinkler Rough-in/Hydro10/1/200710/1/200710/1/2007APART
DetailsForrest France
Overhead install is acceptable, need as-built plans showing field modifications at the escalator.
Issue and Print Permit  8/20/2007  
PLANS/APPL TAKEN TO FRONT DESK  8/17/2007  
Inspection Record Card- Fire8/17/2007 8/17/2007 DONE
Telephone call  8/17/2007 DONE
tlk with tom ###-#### that permit and fees are ready to be picked up
Permit Ready to Issue  8/17/2007 DONE
Sprinkler Plan Check7/31/2007 8/15/2007 PASS
Plans are approved as submitted by bryan johson
Application received  7/31/2007  
Pending Assignment by SAM7/31/2007