INSP-Final Inspection | 9/27/2007 | 10/3/2007 | 10/3/2007 | A | PASS |
Forrest France
|
|
|
Required corrections have been completed, fire sprinkler permit finaled.
|
INSP-Final Inspection | 9/20/2007 | 9/26/2007 | 9/26/2007 | A | PART |
Forrest France
|
|
|
Noted three upright heads at mechanical room 000Y which exceed the max. allowable distance below the deck for proper response time- the mech. piping above the heads does not provide adequate heat collection. The remainder of overhead installation is acceptable.
|
INSP-Final Inspection | 9/18/2007 | 9/21/2007 | 9/20/2007 | P | CANC |
Forrest France
|
|
|
Phone #: ###-#### Internet Inspection Request from: Greg Kirkes Inspection cancelled from web by: Greg Kirkes
|
Plan resubmittals received | | | 9/20/2007 | | PASS |
|
|
|
modified plans approved on site by T. Cobbley.
|
INSP-Final Inspection | 9/17/2007 | 9/19/2007 | 9/18/2007 | A | CANC |
Forrest France
|
|
|
complete fire sprinkler inspection. Phone #: ###-#### Internet Inspection Request from: Greg Kirkes Inspection cancelled from web by: Greg Kirkes
|
Miscellaneous action | | | 9/6/2007 | | PASS |
|
|
|
Approved Special Request for Approval to use the existing design using 1/2" dia CU pipe drops for sprinklers being relocated within this TI area. Refer to attached letter from S.E. Murdock (Micron Mechanical Engineer and sprinkler designer), the original system approval letter by State of ID plan reviewer Lee Bright (dated Aug 2, 1989), and opinion letter from FM engineer D. Burnett dated Sept 5, 2007.
|
Sprinkler Plan Check | | | 9/6/2007 | | PASS |
|
|
|
REvised plan modification; reviewed/approved onsite by TC
|
INSP-Sprinkler Rough-in/Hydro | 8/27/2007 | 8/29/2007 | 8/29/2007 | A | FAIL |
Troy Cobbley
|
|
|
Provide verification that the 1/2" piping to the sprinkler heads and the tape separation on the piping/hangers was allowed under the code in which the buidling was built. See the city approved plans for locations where sprinkler heads need to be changed from 200 to 155 degrees. Also see the plans where the clouded area is the only area not inspected.
|
Sprinkler Plan Check | | | 8/29/2007 | | PASS |
|
|
|
Plan modification approved by T. Cobbley, onsite review; sheets FPD2.0.1 FP2.0.1 and FP6.1
|
CHANGE STATUS TO (ISS) | | | 8/14/2007 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/8/2007 | | DONE |
|
|
|
|
Plan assigned to (Scott) | | | 8/3/2007 | | DONE |
Bill Alexander
|
|
|
This permit was created on the web by Paul Marcolina
|
Application received | | | 8/3/2007 | | DONE |
|
|
|
This permit was created on the web by Paul Marcolina
|
Sprinkler Plan Check | | | 8/3/2007 | | PASS |
|
|
|
On site review byT. Cobbley.
|