Permit Information
Permit NumberFIR07-00697
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 7701 NORTHVIEW
Project NameFairmont Park Elementary
Customer Number 
ePlanReview 
Description
12/28/07 Plan Review Comments
These plans were resubmitted as requested based on the plan review comments dated 11/16/07. The resubmittal also included the As-Built drawings. Revisions are noted as Delta 2.


11/16/07 Revised Scope of Work: Overhead
These plans were resubmitted to as requested based on then plan review comments dated 08/27/07. The resubmittal also included plan modifications of which appear to have been the result of pre-construction coordination with the architect and or the other trades involved in this project.
Scope of Work: Underground & Overhead
Beginning from a 6” x 12” tapping tee off Northview Street, run 140’ of 6” C900 underground piping out and rise up into the bldg with 6” ductile Iron as indicated on sheet FP-1. The riser room of this new 59,007-ft/2 bldg. will be located on the North side. The over head portion of the project includes installing two wet pipe system risers to serve through out the bldg. The exterior canopies shall be constructed of a non-combustible construction there for sprinkler protection will be omitted from those areas. The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD06-03277.03/17/08 Plan Review Comments
These plans were resubmitted based on a failed field inspection. The plans were also modified to include 9 additional heads located in overbuilds that were not originally shown on the plans. The modifications were dated 02/28/08. The revisions are note\d as delta R & A on sheets FP-2 through FP-6. As a result of this resubmittal four sets of calculations were revivified of which 63 total heads were affected. These modifications are subject to field inspection and approval. 04/15/08 Plan Review Comments: These plans were resubmitted based on a failed field inspection performed on 03/21/08. The plans were also modified to include 10 additional heads to meet coverage requirements that were not originally shown on the plans. The modifications were dated 03/25/08. The revisions are note\d as delta 2, 3 & C on sheets FP-2 through FP-6. As a result of this resubmittal four sets of calculations were reviewed of which 54 total heads were affected. These modifications are subject to field inspection and approval.04/15/08 Plan Review Comments
These plans were resubmitted based on a failed field inspection performed on 03/21/08. The plans were also modified to include 10 additional heads to meet coverage requirements that were not originally shown on the plans. The modifications were dated 03/25/08. The revisions are note\d as delta 2, 3 & C on sheets FP-2 through FP-6. As a result of this resubmittal four sets of calculations were reviewed of which 54 total heads were affected. These modifications are subject to field inspection and approval.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection6/25/20086/26/20086/26/2008APASS
DetailsForrest France
Overhead, forward flush and all flow and tamper switches tested.KR
INSP-Sprinkler Rough-in/Hydro5/14/20085/14/20085/14/2008PPASS
DetailsTroy Cobbley
The above ground hydro test passed.
INSP-Sprinkler Rough-in/Hydro5/8/20085/9/20085/9/2008AFAIL
DetailsTroy Cobbley
The above ground hydro test failed.
INSP-Sprinkler Rough-in/Hydro4/22/20084/23/20084/23/2008PFAIL
DetailsTroy Cobbley
The above ground hydro test failed. The kitchen area sprinkler piping can now be covered.
INSP-Sprinkler Rough-in4/17/20084/18/20084/18/2008APART
DetailsTroy Cobbley
Piping is ok to cover except near the cafeteria area due to vapor barrier contacting the upright sprinkler heads and in the classroom where the upright sprinkler heads are located too far from the deck. Also the two uprights at the attic access ladder are too far from the deck. Also the eaves are ok to cover. I let the general contractor know that nearly all of the manual pull stations for the fire alarm system are mounted too high and will need to be lowered.
INSP-Sprinkler Rough-in4/16/20084/17/20084/17/2008APART
DetailsTroy Cobbley
See the city approved plans for areas where the sprinkler piping is ok to cover. Also see the plans for defieciencies found.
Inspection Record Card- Fire4/16/2008 4/16/2008 DONE
DetailsCathy Brown
Telephone call  4/16/2008 DONE
tlk lilly that permit and fees are ready to be picked up
Permit Ready to Issue  4/16/2008  
Issue and Print Permit  4/16/2008  
Miscellaneous action  3/31/2008 DONE
Alternative design request from Hummel Arch's for modification to eave construction in lieu of sprinklers, approved by Fire Department. Faxed to architect. Doc attached.
Plan resubmittals received  3/28/2008  
Received five binders and sheets FP1, FP2, FP3, FP4, FP5, FP6; taken to Fire Review
INSP-Sprinkler Rough-in/Hydro3/20/20083/21/20083/21/2008AFAIL
DetailsTroy Cobbley
I found the sprinkler piping in the Daycare and the next two adjoining rooms sizing did not match plans. 1" piping was installed where 1 1/2" was shown. Also 1 1/2" piping was installed where 2" piping was shown. I went over these discrepancies with the fitter and also contacted Shilos office and spoke to Stan. I stopped the inspection after these three rooms. I let all of the involved parties know that the piping installed needs to match the plans or the plans need to be resubmitted reflecting the actual installation.
INSP-Sprinkler Rough-in3/19/20083/20/20083/20/2008PCANC
DetailsTroy Cobbley
Inspection was scheduled for the afternoon but due to previous commitments at micron I could not due the inspection in the afternoon. I offered to due perform the inspection in the morning but Mike Meyers had other commitments in Middleton. Mike and I agreed to meet at 8:30 friday morning.
PLANS/APPL TAKEN TO FRONT DESK  3/19/2008 DONE
Inspection Record Card- Fire3/19/2008 3/19/2008 DONE
DetailsCathy Brown
Telephone call  3/19/2008 DONE
tlk to lillie ###-#### that permit and fees are ready to be picked up
Permit Ready to Issue  3/19/2008 DONE
Issue and Print Permit  3/19/2008 DONE
Sprinkler Plan Check3/7/2008 3/17/2008 PASS
Details
This was the 5th review of these plans. As a result of this review, 63 heads were affected due to plan modifications.
Bryan Johnson
Plan resubmittals received  3/7/2008  
received appliation, five binders of submittal info and five copies of sheets FP1, FP2, FP3, FP4, FP5, FP6; taken to fire review
INSP-Sprinkler Rough-in2/27/20082/28/20082/28/2008APART
DetailsTroy Cobbley
The inspection today was only for the cafeteria. One truss in the southwest corner had been damaged as a result of the improper installation of a sprinkler pipe hanger. I contacted Jim Sly and described the problem to him. Jim said it should not be an issue. Additional insulation was required above the upright heads in the northwest corner of the cafeteria and it was installed as I waited. It appears that all of the hangers that I spot checked today were in need of relocating as based on yesterdays inspection. I gave the general contractor permission to cover just the cafeteria and a small rectangular storage room on the west side of the gymnasium. A representative of Kreisenbeck Construction again asked if the classrooms could be covered. I stated that if the were covered all ceiling tile would have to be removed for my inspection. I also stated that myself and Jim Sly had told Nacho previously that no ceilings were to be installed.
Plan assigned to (OutSourced)2/28/2008 2/28/2008 DONE
DetailsCathy Brown
INSP-Sprinkler Rough-in2/26/20082/27/20082/27/2008PFAIL
DetailsTroy Cobbley
This is for the cafeteria. Inspection for the cafeteria failed due to upright heads located in the northwest corner being too far down from the deck. Per Mike insulation will be installed to match the other areas. Also the first hanger attachment I checked was not installed per NFPA 13 - 9.1.5.6.1. Piping cannot be covered in the cafeteria until I can reverify these two items. Shilo Automatic Sprinkler and the general contractor requested permission to cover the piping in all of the classrooms. I denied this request due to acces to the piping for inspection. Also the piping as installed is not approved at this time.
Case Summary  2/19/2008  
INSP-Supply line flush2/13/20082/14/20082/14/2008APASS
DetailsTroy Cobbley
The underground flush passed. I did a quick walk through while waiting and found the t-bar is being installed as well as some ceiling tiles/lights. I notified the project superintendant that no ceiling are to be installed or sprinkler piping to be covered since the sprinkler system has not been inspected yet. Jim Sly the structural inspector has also been notified.
INSP-Sprinkler Rough-in2/8/20082/11/20082/11/2008PFAIL
DetailsTroy Cobbley
Mike wanted me to just inspect the cafeteria today. I found that the pipe sizes as shown on the approved plans for this area do not match what is installed. Infact the unapproved as-builts that the fitter had do not match the installation. No piping is to be covered. Correct as-built plans need to be submitted and approved.
INSP-Supply line flush2/7/20082/8/20082/8/2008ACANC
DetailsTroy Cobbley
Mike M is the contact. Thanks Phone #: ###-#### Internet Inspection Request from: Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in2/7/20082/8/20082/8/2008ACANC
DetailsTroy Cobbley
Mike M is the contact. Thanks Phone #: ###-#### Internet Inspection Request from: Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in2/6/20082/7/20082/7/2008PCANC
DetailsTroy Cobbley
Inspection canceled due to time constraints. (Micron plan review) Mike M. was notified of this midmorning.
INSP-Sprinkler Rough-in1/9/20081/10/20081/10/2008PPART
DetailsTroy Cobbley
Only the piping above the hard lid areas as marked on the plans is ok to cover. Per the sprinkler fitter the plans are being resubmitted with the installation changes. I started to do a rough-in inspection but found heads added in the attic space and the piping configuration changed. It appears that instead of 12 heads supplied by 2" piping there are now 15 heads supplied from the 2" supply. This was on the first line I looked at. The piping configuration was the issue in two of the only two areas I looked at. I stopped the inspection at this point. On the way out of the building I noticed that the building eaves are combustible concealed spaces that will require sprinkler protection as per NFPA 8.14 or at a minumum meet one of the 15 exceptions as listed in the same section. I left a correction notice with the job superintendant.
Issue and Print Permit  1/2/2008 DONE
PLANS/APPL TAKEN TO FRONT DESK  12/31/2007  
Telephone call  12/31/2007 DONE
tlk to lilly ###-#### that permit and fees are ready to be picked up
Permit Ready to Issue  12/31/2007 DONE
Inspection Record Card- Fire12/31/2007 12/31/2007 DONE
DetailsCathy Brown
Permit Ready to Issue  12/31/2007 DONE
Sprinkler Plan Check12/19/2007 12/27/2007 PASS
Details
Note: This was the 3rd review of theses plans. As-Built plans are approved by Bryan Johnson

Plan resubmittals received  12/19/2007  
received five copies of appliation, submittal info and pages FP1, FP2, FP3, FP4, FP5, FP6; taken to fire review
Miscellaneous action  11/28/2007 DONE
Early Start request approved. Doc Attached. Discussed criteria for Early Start with Randy Knudson; ES's are not intended to include situations where the permit has not been issued due to the contractor not responding to review comments in a timely fashion.
Sprinkler Plan Check11/16/2007 11/16/2007  
The plans were denied due to missing or inaccurate information. Upon request, the denied set may retrieved from my office for salvage. The denied set will be maintained for 5 working days.
Plan resubmittals received  11/5/2007  
Application received  8/9/2007  
Pending Assignment by SAM8/9/2007    
Plan assigned to (SAM)3/28/2008    
resubmittals submitted