INSP-Final Inspection | 11/26/2007 | 11/26/2007 | 11/26/2007 | P | PASS |
Troy Cobbley
|
|
|
Permit passed. Forward flush passed.
|
INSP-Sprinkler Rough-in/Hydro | 11/21/2007 | 11/21/2007 | 11/21/2007 | P | PASS |
Troy Cobbley
|
|
|
Above ground hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 11/20/2007 | 11/20/2007 | 11/21/2007 | P | PASS |
Troy Cobbley
|
|
|
Need backflow certified, hydro test completed and the forward flush performed. Also need the fire alarm interconnections tested.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/14/2007 | | |
|
|
|
|
Inspection Record Card- Fire | 9/14/2007 | | 9/14/2007 | | DONE |
|
|
|
|
Telephone call | | | 9/14/2007 | | DONE |
|
|
|
tlk to brodie ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 9/14/2007 | | |
|
|
|
|
Issue and Print Permit | | | 9/14/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 8/24/2007 | | 9/12/2007 | | PASS |
|
|
|
Plans are approved w/conditions by Bryan Johnson
|
Application received | | | 8/24/2007 | | |
|
|
|
|
Pending Assignment by SAM | 8/24/2007 | | | | |
|
|
|
|