Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberFIR07-00755
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 2223 W AIRPORT WAY
Project NameAirport Business Center B
Customer Number 
ePlanReview 
Description
The Permitted Work Scope:
Modify an existing wet pipe system by tying into the existing 4” wet supply pipe to feed a new 4” Double interlock preaction valve to serve the switch equipment rooms. This building is fully fire sprinklered. This fire protection work shall comply with the IFC 2003 and the permit review comments; each regulated by the Fire Chief. The review comments, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to BLD07-01422.
When tenant work affects fire sprinkler protection outside the permitted work area due to the installation of tenant-demising or new partition walls, the affected area sprinkler coverage outside the BLD permit will fall under the Fire Permit scope of work, to maintain the required fire protection within the fire sprinklered facility. The “Riser” and its supplies which include all appurtenances (including tamper, alarm and alarm monitoring) relating to the normal and correct function and integrity of this system will fall under the jurisdiction for code compliant verification.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/7/200711/8/200711/8/2007PPASS
DetailsForrest France
Do a full function test on preaction system.Verifie flow, tamper and alarm to main panel and clean agent fike panel.
INSP-Sprinkler Rough-in/Hydro11/7/200711/7/200711/7/2007PCANC
DetailsForrest France
javier Phone #: ###-####
INSP-Sprinkler Rough-in/Hydro10/4/200710/5/200710/5/2007APART
DetailsForrest France
Pneumatic testing for the preaction system passed.
INSP-Sprinkler Rough-in/Hydro10/3/200710/4/200710/4/2007APART
DetailsForrest France
Added heads below ductwork are acceptable, okay for cover at the drop ceilings, begin pneumatic testing @ 40psi at 10:15 AM for the preaction system.
INSP-Sprinkler Rough-in/Hydro9/21/20079/24/20079/24/2007APART
DetailsForrest France
OH rough-in for the new preaction and wet systems completed, noted blocked heads by ductwork over 4' in width will require added heads at five locations, riser is not completed at this time, areas at the drop ceilings are okay for cover, AG hydrostatic testing passed, need to perform 24 hr. pneumatic test on the preaction system.
PLANS/APPL TAKEN TO FRONT DESK  9/14/2007 DONE
Inspection Record Card- Fire9/14/2007 9/14/2007 DONE
Telephone call  9/14/2007 DONE
TLK TO BRODIE THAT PERMIT AND FEES ARE READY TO BE PICKED UP
Permit Ready to Issue  9/14/2007 DONE
Issue and Print Permit  9/14/2007 DONE
Miscellaneous action  9/13/2007 DONE
Early Start Request approved. Copy attached.
Sprinkler Plan Check8/29/2007 9/13/2007 PASS
Plans are approved w/conditions by bryan johnson
Application received  8/29/2007  
Pending Assignment by SAM8/29/2007