INSP-Final Inspection | 11/27/2007 | 11/27/2007 | 11/27/2007 | P | PASS |
Troy Cobbley
|
|
|
Underground fire permit finaled
|
INSP-Final Inspection | 11/19/2007 | 11/19/2007 | 11/19/2007 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given by dave hanniman until the fire sprinkler drawings have been resubmitted and all changes approved including the new piping to the shed and roof top doghouses.
|
INSP-Final Inspection | 11/16/2007 | 11/19/2007 | 11/19/2007 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given by dave hanniman until the fire sprinkler drawings have been resubmitted and all changes approved including the new piping to the shed and roof top doghouses.
|
INSP-Final Inspection | 11/14/2007 | 11/14/2007 | 11/14/2007 | P | CANC |
Troy Cobbley
|
|
|
Contact is Trent Bice. Phone #: ###-#### Internet Inspection Request from: Trent Bice
|
INSP-Sprinkler Rough-in/Hydro | 11/14/2007 | 11/14/2007 | 11/14/2007 | P | CANC |
Troy Cobbley
|
|
|
Contact is Ryan Jensen. Phone #: ###-#### Internet Inspection Request from: Trent Bice
|
INSP-Sprinkler Rough-in | 10/22/2007 | 10/22/2007 | 10/22/2007 | P | PASS |
Troy Cobbley
|
|
|
The deficiencies have been corrected and the sprinkler piping is ok to cover. I found one overspaced head just inside of the entry vestibule. I notified Trent of this and told him I would verify the installation at the final.
|
INSP-Sprinkler Rough-in | 10/18/2007 | 10/19/2007 | 10/19/2007 | P | CANC |
Troy Cobbley
|
|
|
Contractor is not ready for the rough-in inspection. Will need to be rescheduled for Monday.
|
INSP-Supply line flush | 10/18/2007 | 10/19/2007 | 10/19/2007 | A | PASS |
Troy Cobbley
|
|
|
The underground flush passed.
|
INSP-Sprinkler Rough-in | 10/18/2007 | 10/19/2007 | 10/18/2007 | A | CANC |
Troy Cobbley
|
|
|
Requesting a rough to cover inspection.
Phone #: ###-#### Internet Inspection Request from: Trent Bice Inspection cancelled from web by: Trent Bice
|
INSP-Sprinkler Rough-in/Hydro | 10/10/2007 | 10/10/2007 | 10/10/2007 | P | PASS |
Troy Cobbley
|
|
|
The underground hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 9/18/2007 | 9/19/2007 | 9/19/2007 | A | PASS |
Troy Cobbley
|
|
|
The remaining undergrond supply piping is ok to cover.
|
INSP-Sprinkler Rough-in/Hydro | 9/17/2007 | 9/17/2007 | 9/17/2007 | P | FAIL |
Troy Cobbley
|
|
|
The underground supply at the 90 degree fitting is still too shallow and will need to be lowered and reverified at inspection. I gave the ok to cover on the remaining straight run to the United Water tap.
|
INSP-Sprinkler Rough-in/Hydro | 9/14/2007 | 9/14/2007 | 9/14/2007 | P | FAIL |
Troy Cobbley
|
|
|
The remaining underground supply piping is not buried deep enough. Do not cover piping.
|
INSP-Sprinkler Rough-in | 9/11/2007 | 9/12/2007 | 9/12/2007 | A | PART |
Troy Cobbley
|
|
|
The 5'-0" stub out is ok to cover. As measured it does not have the 4'-6" required bury. The top of pipe is 6'-2" from the top of the foundation. The general contractor assured me that once the finish grade and landscaping is complete the piping would have the required 4'-6" bury. If it does I notified him it would need to be dug up and installed at the correct depth.
|
Sprinkler Plan Check | 8/30/2007 | | 9/11/2007 | | DONE |
|
|
|
plans are approved as submitted by bryan johnson
|
Inspection Record Card- Fire | 9/11/2007 | | 9/11/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/11/2007 | | DONE |
|
|
|
|
Telephone call | | | 9/11/2007 | | DONE |
|
|
|
left message w michelle for trent bice at ###-#### - permit ready and fees given
|
Issue and Print Permit | | | 9/11/2007 | | DONE |
|
|
|
|
Telephone call | | | 9/4/2007 | | DONE |
|
|
|
telcon form Trent with Phoenix regarding turnaround time for plan approval. I indicated he could cancel this permit (come pick up the plans) and submit this as a Quick permit, following the applicable quick permit submittal guidelines. He may do that.
|
Application received | | | 8/30/2007 | | |
|
|
|
|
Pending Assignment by SAM | 8/30/2007 | | | | |
|
|
|
|