INSP-Final Inspection | 3/4/2008 | 3/4/2008 | 3/4/2008 | A | PASS |
Forrest France
|
|
|
Fire sprinkler final inspection passed, missing calc. sticker at the riser to be provided as discussed.
|
INSP-Supply line flush | 3/4/2008 | 3/4/2008 | 3/4/2008 | P | PART |
Forrest France
|
|
|
UG fire supply line flush completed satisfactory.
|
INSP-Final Inspection | 3/3/2008 | 3/3/2008 | 3/4/2008 | P | DEFR |
Forrest France
|
|
|
bill Phone #: ###-####
|
INSP-Supply line flush | 3/3/2008 | 3/3/2008 | 3/3/2008 | P | DEFR |
Forrest France
|
|
|
To be completed on 3/4 as discussed.
|
INSP-Supply line flush | 2/29/2008 | 3/3/2008 | 3/3/2008 | A | NR |
Forrest France
|
|
|
UG flush rescheduled per contractor.
|
INSP-Sprinkler Rough-in | 10/22/2007 | 10/23/2007 | 10/24/2007 | A | PART |
Forrest France
|
|
|
OH rough-in is approved for cover, noted riser is not yet complete.
|
INSP-Sprinkler Rough-in | 10/19/2007 | 10/22/2007 | 10/22/2007 | A | CANC |
Troy Cobbley
|
|
|
Cancelled per bill Phone #: ###-####
|
Inspection Record Card- Fire | 10/15/2007 | | 10/15/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/15/2007 | | DONE |
|
|
|
|
Telephone call | | | 10/15/2007 | | DONE |
|
|
|
t/c w jon edes at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 10/15/2007 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/15/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 9/27/2007 | | 10/11/2007 | | PASS |
|
|
|
plans and calculations are approved as submitted by bryan johnson
|
Miscellaneous action | | | 10/2/2007 | | FAIL |
|
|
|
early start request not approved. Called Jon Edes, left voice message explaining reason: does not meet criteria # 2, 3, 4 also need to sign the request (#9) .
|
Case Summary | | | 9/27/2007 | | DONE |
|
|
|
|
Application received | | | 9/27/2007 | | |
|
|
|
|
Pending Assignment by SAM | 9/27/2007 | | | | |
|
|
|
|